1. Bidding conditions
The name of this bidding seabet my is PC construction general contracting of Shandong Green Energy Dingtao 50MW wind power seabet my,The tenderer is Shandong Green Energy Investment Co., Ltd.,The seabet my unit is Heze Luyuan New Energy Co., Ltd. (contract signing party),The source of funds is self-raised funds,This seabet my has met the bidding conditions,Now open bidding for this seabet my。
2. seabet my Overview and Bidding Scope
2.1Project Overview、Bidding scope and bid section (package) division:
2.1.1 seabet my Overview:
Shandong Green Energy Dingtao 50MW wind power seabet my is located in Rantan Town, Dingtao District、Nanwangdian Town、In Maji Town,The wind farm site area is about 30km2。The seabet my site range is about 27km from east to west,North and South 8km,There is highway G35 near the venue、Lancao Expressway (under construction) and Provincial Highway S351、S259、S261,There is also a road connecting the village to the outside world,Altitude between 45m~55m。
The construction scale of this seabet my is 50MW,A total of 5 wind turbine units with a single unit capacity of 3600kW and 8 units with a single unit capacity of 4000kW (13 units in total) are installed,The seabet my clearance limit is 270 meters above sea level。13 wind turbines are connected to the established 110/35kV step-up substation through 2 35kV collector lines, 35kV incoming line interval。A new 110kV booster station has been built in the preliminary seabet my,A 50MW main transformer and corresponding 110kV/35kV intervals have been built at the booster station,In this phase, a 50MW main transformer and corresponding 110kV/35kV intervals are expanded。Main electrical wiring: The 110kV side is expanded from line transformer group wiring to single busbar wiring in this phase,Newly build a 50MW main transformer,The 50MVA main transformer on the 35kV side adopts single busbar segmented wiring。
2.1.2 Bidding scope and bidding section (package) division:
This seabet my is divided into 1 bidding section.
Tender scope:
Shandong Green Energy Dingtao 50MW wind power seabet my PC construction general contracting and procurement、Construction general contracting seabet my,Mainly including but not limited to:
(1) Equipment procurement scope: all equipment and materials that meet the installation requirements of this seabet my (wind turbines、Tower、After the anchor bolts and other materials are purchased through bidding by the contractor,Perform contract transfer,Included into the management scope of PC general contractor),Including but not limited to: fans、Tower、Anchor、Box type transformer、cable、Main transformer of collector line and booster station extension、Power distribution device、Reactive power compensation、Switch cabinet、Expansion part of electrical secondary equipment (including comprehensive automation、Network-related equipment、Communication Equipment、Primary frequency modulation equipment, etc.) and other hardware and software equipment、Firefighting facilities and corresponding technical services,Various equipment, materials and services that meet the technical requirements of wind farms in the bidding documents,And supervision of equipment within the procurement scope、Urgent delivery、Transportation、Pick up、Unlucky (including storage yard)、Acceptance of goods (including third-party inspection required by specifications)、Warehousing, storage, etc.。
(2) Construction scope: road engineering of this seabet my (including approach road、Roads within the venue,Including new roads and repairs of old roads)、Fan and box transformer foundation seabet my、Installation, commissioning and trial operation of all equipment (including fans、Tower)、Wind power forecast expansion、35kV collector line construction seabet my、110kV booster station expansion 110kV power transformation and distribution structure seabet my、Spanning (crossing) involved in the transportation of large equipment、Relocation line、Demolition、Coordination, etc.,Fire protection engineering (extension)、Grounding works and ancillary works (extension part)、Construction of on-site communication engineering and water and power supply (surrounding ecological environment protection during the process、Domestic water source protection and management、Water Conservation、Environmental protection measures guarantee)、Pile foundation inspection、Finished product care、Green vegetation restoration seabet my after completion、Environmental Protection seabet my、Soil and water conservation seabet my (meeting relevant requirements for approval and acceptance),Domestic water and electricity、Coordination of land acquisition, coordination of construction and various coordination in the process、Acceptance (including but not limited to files、Environmental protection、Water Conservation、Firefighting、Planning、Energy saving、Complete acceptance of electromagnetic radiation, etc.),And finally deliver the whole process contracting of grid-connected power generation in accordance with the requirements of the contractor。
The scope of this bidding does not include the 110kV transmission line and the opposite station reconstruction seabet my。This part has been completed in the preliminary engineering。
(3) Procedure scope:
①The whole construction period of the seabet my and the long-term leased forest land、Land、Demolition、Relocation of above-ground and underground lines、Cemetery、Greenhouse、Well、Compensation (such as young crop compensation、Forest land compensation、Production reduction compensation, etc.)、Lease fee、Reclamation fee (including construction fee、Reclamation deposit and other fees)、Coordination、All fees and procedures involved in surface attachments (land transfer fee、Except farmland occupation tax and land use tax)。Including construction period and long-term expropriation、Lease coordination fee,Excluding land transfer fee、All costs involved in land acquisition except farmland occupation tax and land use tax。The contractor is only responsible for the review and payment of permanent land occupation and long-term land lease fees,Coordination and all other work shall be the responsibility of the contractor。
② Various procedures from the early stage of the seabet my to the seabet my put into operation (such as: construction permit,Grid connection, etc.),Relocation line、Meteorology (Lightning Protection)、Energy saving、Firefighting、Quality Supervision、Special acceptance and procedures for grid connection and other matters (obtain relevant documents),And bear the expenses。Responsible for handling construction permits、State-owned land use right certificate、Land planning permit、seabet my Planning Permit、Real estate certificate, etc.。
③Technical services related to this seabet my,Like factory training、On-site training、Device debugging、Unit trial operation、Wind turbine operation and maintenance services during the warranty period、Warranty services for towers and other electrical equipment, etc.。Equipment installation、Debug、Test、Inspection and testing required by power grid companies at all levels、Electric secondary security protection evaluation、Test、Grid-connected trial operation、Elimination、Acceptance,Handle all construction and safety risks related to the seabet my (the beneficiary is the tenderer)、Third party liability insurance。Complete acceptance and seabet my handover、Related work on the acceptance of archival materials,And all work related to general contracting projects。
(4) Tools and spare parts: Party B is responsible for purchasing the production operation and maintenance tools necessary for equipment operation and maintenance、Spare parts,The list is to be filled in by the bidder。
(5) Other scope of work: including but not limited to: all government coordination、Local relationship handling、Civil Coordination、External coordination and cost payment such as temporary and long-term land acquisition coordination,Equipment procurement for wind power projects、Material Procurement、Transportation and on-site storage management、Construction (including preliminary preparations for construction)、Debug、Completion acceptance;Permanent land acquisition procedures and fees (except land transfer fee、All expenses related to land acquisition except farmland occupation tax and land use tax) payment;Coordination of temporary land lease and payment of fees during the seabet my construction period and coordination of land lease during the operation period;In all wind farms、seabet my construction in booster station;Approach Road、Temporary construction road on site、Construction and acceptance of permanent maintenance roads;Installation and debugging of fans and ancillary equipment;Wind turbine generator、Send、Trial operation of substation system、The defect elimination and wind turbine successfully passed 250 hours of grid-connected commercial operation and completion acceptance;Path protocol for on-site collector lines、Construction and acceptance;Construction period engineering insurance;Processing procedures for seabet my start;Processing land procedures;Road、Railway、river、Line、Communication、Following the procedures for crossing (crossing) underground obstacles;Soil and Water Conservation Supervision、Soil and Water Conservation Monitoring;seabet my acceptance;All special acceptance related to this seabet my (including but not limited to: planning、Energy saving、Firefighting、Environmental protection、Water Conservation、File、Occupational hazards, etc.)、Safety and quality supervision inspection and acceptance、Grid connection and related procedures、Power quality detection、Classification protection assessment and filing、seabet my data file organization、A "turnkey seabet my" for all work including handover and special acceptance of files、Transfer and service during the warranty period,And meet the requirements of the contracting party to meet the standard and start production、Passed acceptance by the contractor。Also includes all necessary engineering deficiencies、Material、Spare parts、Special tools for production safety、Consumables and related technical information and personnel training,Various meetings during the construction period,seabet my data includes but is not limited to process data、Annex 15 of Completion Documents Transfer Contract Format, etc.。
(6) This bidding does not include seabet my supervision.
(7) The contractor’s quality of the general contracting seabet my、Safety、Construction period、Be fully responsible for cost and environmental protection。
(8) All income from the electricity sales of this seabet my belongs to Party A.
(9) This seabet my is a “turnkey seabet my”,Procedures encountered during seabet my construction、Coordination、Payment、Work、Acceptance, etc.,Unless the contract clearly stipulates that Party A is responsible,Regardless of whether it is included in the bidding bill of quantities,all belong to the scope of work of Party B。
(10) If the bidder cannot respond to all the requirements of the bidding documents,Discrepancies should be clearly stated in a separate document,Otherwise, regardless of whether the content of the bidding document is consistent with the requirements of the bidding document,It is deemed that the bidder has responded to all requirements of the bidding documents。
The warranty period of this seabet my shall comply with relevant national regulations (the warranty period of the complete fan is 5 years)。
See Chapter 5 for details.
2.2 seabet my construction period: The fan foundation will be poured before March 10, 2022,Full capacity grid connection on September 30, 2022。If it cannot be connected to the grid at full capacity before September 30, 2022,then every extension is 1 day,The fine amount is 0 of the total contract price.1%。If it cannot be connected to the grid at full capacity before December 30, 2022,Policy risks and economic losses caused by failure to connect to the grid on time,All are borne by the bidder。
Start time: March 10, 2022 (based on pouring the first concrete of the fan foundation,The specific seabet my period shall be subject to the start date issued by the contractor)。
2.3according to country、Shandong Province、Heze City and Dingtao District Local Government Epidemic Prevention and Control Systems and Requirements,The bidding unit needs to investigate the control requirements of the seabet my location,Develop a special "whole-process epidemic prevention and control system",Guarantee projects continue to advance steadily in accordance with national epidemic prevention requirements。
3. Bidding conditions
3.1 Bidder qualifications, capabilities and credibility requirements:
[1]Qualification requirements:
(1) The bidder must be an independent legal person or other organization registered in accordance with the law,Valid supporting documents must be provided。
(2) Bidders should have the following qualifications:
(a) First-level qualification for power engineering seabet my general contracting,Decoration (Repair、Trial) Level 1 Qualification,Engineering Design Power Industry Grade A;
(b) Valid production safety license.
(3) The bidder must have and provide effective quality、Environment、Occupational Health and Safety Management System Certification Certificate。
[2] Performance requirements: Bidders should have completed PC general contracting or EPC general contracting performance of at least 400,000 kilowatt wind power projects in the past five years (January 2016 to present)。The bidder must provide a contract that can prove the performance requirements of this bidding and corresponding seabet my completion certification materials,Contract materials must contain at least: page with seals of both parties to the contract、Contract signing date、Contract scope content and key technical parameters and other information;Proof of seabet my completion should be one of the following: State Electricity Regulatory Commission document、seabet my Start Handover Signature、Transfer of appraisal certificate、Production certificate、Completion Certificate、Grid connection certificate、Completion acceptance report。
[3] Financial requirements: Provide financial statements (from 2018 to 2020) issued by an audit agency or a certified public accounting firm;(need to include balance sheet、Cash flow statement、Copy of income statement,Missing any item is considered not provided),If the 2018-2020 audit report or financial statements cannot be provided,Relevant certificates are required if the company has been established for less than three years,Resulting in the inability to provide the above financial statements,Provide financial statements issued by audit institutions or certified public accounting firms since the company’s establishment;(need to include balance sheet、Cash flow statement、Copy of income statement,Missing any item is considered not provided)。
[4] Credibility requirements: Bidder’s social credibility self-examination commitment from January 1, 2019 to present (stamped with company seal、Customized format);Bidders need to provide the "China Execution Information Disclosure Network" website (http://zxgk when registering.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty。The tenderer shall impose restrictions on dishonest persons who are restricted from participating in bidding activities for engineering seabet my projects in accordance with laws and regulations。
[5]Qualification requirements for seabet my managers:
(1) The bidder must provide the proposed seabet my manager’s valid registered first-class construction engineer qualification certificate (mechanical and electrical engineering major)、Valid Class B safety production assessment certificate and senior engineer title。
(2) The proposed seabet my manager must have the performance of at least one PC general contracting or EPC general contracting seabet my manager for wind farms of 48MW and above,The bidder must provide supporting documents that prove the performance of the seabet my manager,It can be a contract or acceptance certificate or user certificate and other stamped materials (the above materials must reflect the name of the seabet my、seabet my Manager、Completion/commissioning time and unit name)。At the same time, the social security certificate of the seabet my manager who has worked for the bidding unit for the past one year must be provided。
[6] Qualification requirements for seabet my leaders:
(1) The bidder must provide the proposed seabet my responsible person with a valid first-class registered seabet my engineer qualification certificate (seabet my engineering or mechanical and electrical engineering major) and a valid Class B safety production assessment certificate。
(2) The construction leader must have at least 2 experiences as the construction leader of wind farms of 48MW and above,The bidder must provide supporting documents that can prove the performance of the person in charge of the construction,It can be a contract or acceptance certificate or user certificate and other stamped materials (need to include the name of the seabet my、Construction manager、Completion/commissioning time and unit name)。
[7] seabet my management organization and personnel: The bidder must provide the valid "Safety Management Personnel Qualification Certificate" C certificate of the proposed safety person in charge。
[8] Requirements for purchasing goods: The contractor’s subcontracting procurement bidding method and scoring standards are required to be consistent with the PC general contracting bidding methods and scoring standards,The subcontracting bidding plan must be reviewed and approved by the contractor。
[9]Other requirements: /.
The qualifications and performance of parent and subsidiary companies shall not be borrowed from each other.
3.2 This seabet my does not accept consortium bids.
4. Obtaining bidding documents
4.1 Time: 09:00 on January 8, 2022 to 17:00 on January 12, 2022,(Beijing time,Except legal holidays),Information required to obtain documents: ①Business license、Qualification certificate ② Authorization letter of legal representative and ID card of the authorized person ③ Performance contract and corresponding seabet my completion certification materials ④ Financial status statement ⑤ Bidder's credit self-examination commitment and the "China Execution Information Disclosure Network" website ( http://zxgk.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty ⑥ Personnel qualification certificate and relevant supporting materials required by the personnel ⑦ Bidding document fee remittance voucher ⑧ Bidder information registration form,Customized format,Including bidder’s name、Contact、Contact information、Basic information such as email address。
The bidder shall send a scanned copy of the original documents above (the picture must be clear and legible) (pdf format) to sdzb1110@163.com,After successful sending, call the agency for review and confirmation
4.2 Bidding document price: 750 yuan/copy,No refund upon sale (only business-to-business transfers accepted,Personal transfers are not accepted,Please note the item number when remitting)。
Tender document fee account:
Company name: Shandong Tendering Co., Ltd.
Account opening bank: Bank of China Jinan Wenhua Road Branch
Bank account number: 227305483177
Line number: 104451038330
4.3Potential bidders who have not obtained the bidding documents in accordance with the requirements of this announcement shall not participate in the bidding。
5. Submission of bid documents and bid opening
Submission deadline: 9:30 on January 28, 2022;
Submission method: paper documents submitted on site;
Submission address: Conference Room on the second floor of Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。
6. Bid opening time and place
Bid opening time: 9:30 on January 28, 2022;
Bid opening location: Conference Room on the second floor of Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。
7. Media for publishing announcements
This bidding announcement is also on the China Bidding and Bidding Public Service Platform (http://www.cebpubservice.com/)、Shandong Procurement and Tendering Network (http://www.sdbidding.org.cn)、Sunshine Procurement Service Platform (http://www.ygcgfw.com/)、Shandong Development Investment Holding Group Co., Ltd. website (//www.sdfztz.com/)。
8.Contact information
Tenderer: Shandong Green Energy Investment Co., Ltd.
Tenderer’s address: Building 108, Guohua Dongfangmei County, Jinan City, Shandong Province
Contact person of the tenderer: Zhou Ruotong
Tenderer’s contact number: 0531-86195997
Agency: Shandong Tendering Co., Ltd.
Agent address: No. 13, Wenhua West Road, Lixia District, Jinan City
Agent Contact: Li Gong
Agent contact number: 0531-81917677、18763988068
Agent email: sdzb1110@163.com
Shandong Development Investment Holding Group Co., Ltd. Copyright 2019 All rights reserved Lu ICP No. 16018610
Address: Shandong Development Building, the intersection of Haiyou Road and Xingong North Street, Lixia District, Jinan City, Shandong Province