(Project number:0627-24101511558

seabet sports betting

The name of this bidding project is Baiyin Jingtai Longlu Development New Energy Co., Ltd. (Jingtai) Zone F 200,000 kilowatt wind power project、330kV booster station expansion project supervision service project,The source of project funds is self-raised funds,The tenderer is Baiyin Jingtai Longlu Development New Energy Co., Ltd.。This project has met the bidding conditions,The current bidding method is public bidding。

2. Project Overview and Bidding Scope

2.1. Project Overview:

(1) (Jingtai) Zone F 200,000 kilowatt wind power project

The wind farm in this phase of the project plans to install 35 units with a single capacity of 5.56MW and 1 unit 5.4MW wind turbine set。This project is located in Jingtai County, Baiyin City, Gansu Province,The wind farm area is a low hilly terrain,The altitude is between 1800m~2000m。There is G338 National Highway near the wind farm site、G2012 Dingwu Expressway、Wuma Expressway and S201 Provincial Highway pass by,Convenient transportation。

The installed capacity of this project is 200MW,Connected to Baiyin Jingtai Longlu Development New Energy Co., Ltd. (Jingtai) Zone A 400,000 kilowatt wind power project booster station through 35kV collector line,50MW of which is connected to the 35kV side of the main transformer of the wind farm in Area A,The remaining 150MW is connected to a 150MVA seabet iothree-phase three-winding seabet betting platform(the third winding is a balanced winding) power transformer installed in the booster station in Area A of this project。The main transformer is connected to the 110kV busbar of the booster station at one 110kV main transformer incoming line interval,Sent out uniformly from the Zone A wind farm project。

Project planned construction period: start in August 2024,Full capacity grid connection in March 2025。

(2) 330kV substation expansion project

Jingtai South (Ruizhu) 330kV substation No. 4 main transformer expansion project: This phase expands the No. 4 main transformer (240MVA) of the Ruizhu substation 330kV substation and the corresponding 330kV interval、110kV interval。

Project planned construction period: start in September 2024,Complete and put into operation in March 2025。

2.2. Bidding scope and bid section (package) division:

This project is divided into 1 bidding section.

Tender scope:

(1) (Jingtai) Zone F 200,000 kilowatt wind power project

Full process supervision services from engineering design to completion acceptance,Includes booster station expansion、Approach Road、Fan and box transformer basics、Fan and box-type transformer crane installation、Collection circuit、Inspection Road、Environmental protection project、Soil and Water Conservation Project、Reclamation project and other sub-projects and all equipment、Material entry acceptance work and equipment installation process control and installation acceptance, etc.;Divided by stages: construction preparation、Construction Stage、Debug phase、Defect liability period stage supervision service。

When the project starts,The supervision unit should be based on the actual needs of the project,Equipped with professional and complete supervisory personnel responsible for the supervision of wind farm projects,At the same time, relevant professional supervisors should be specially assigned to supervise the booster station project,And without the permission of the tenderer,The supervisors responsible for the booster station project and the supervisors responsible for the wind farm project shall not be randomly assigned。

(2) 330kV substation expansion project

Full process supervision services from engineering design to completion acceptance,Including civil engineering、Electrical equipment installation、Debug、Environmental protection project、Soil and Water Conservation Project、Reclamation project and other sub-projects and all equipment、Material entry acceptance work and equipment installation process control and installation acceptance, etc.;Divided by stages: construction preparation、Construction Stage、Debug phase、Defect liability period stage supervision service。

When the project starts,The supervision unit should be based on the actual needs of the project,Equipped with professional and complete supervisory personnel。

2.3.The normal construction period is the construction period + final work processing, completion acceptance, etc. (about 6 months)。The service period is calculated by accumulating the actual entry and actual departure times,The intervening time is not included。

2.4. Project quality requirements:

(1) Achieve high-level standard production,The main technical and economic indicators have reached the design value,Creating the same region in the country、Same period、Advanced level of similar projects。

(2) The quality of the project meets current national standards and regulations、Specification requirements,Realizing engineering and equipment safety、Stable、Economy、Environmental protection、Long cycle operation。

(3) No quality accidents will occur.

2.5. Engineering safety, health and environmental requirements:

No accidents involving minor personal injury or above;

No general or above fire accidents;

No collapse (collapse, collapse) accident;

No general or above mechanical equipment accidents;

No general or above liability traffic accidents;

No general or above electrical safety accidents;

No equipment theft accidents during construction;

No group petition event occurs;

Prevent general and above environmental pollution accidents;

Environmental protection projects and main projects are invested simultaneously;

Prevent dust pollution at the construction site;

Put an end to occupational disease records;

Avoid construction noise disturbing residents;

Zero radiation injury incidents;

Zero food poisoning incidents;

Office、Life、The treatment rate of hazardous waste generated by project construction reaches 100%。

3. Bidder qualification requirements

3.1. Bidder qualifications, capabilities and credibility requirements:

[1]Qualification requirements:

(1) The bidder is a unit or other organization with independent legal personality registered in the People’s Republic of China,Have a valid business license,Must have project performance capabilities,And in staff、Equipment、Having the ability to undertake bidding projects in terms of funds and other aspects,Have a good record of paying taxes and social security funds in accordance with the law。

(2) The bidder must have and provide valid comprehensive qualifications for engineering supervision companies or professional Grade A qualifications for power engineering。

[2]Performance requirements: January 1, 2021 to the bidding deadline (subject to the time of production),The bidder must have at least 2 contract performance of 200MW and above wind power projects at the same time,And at least 2 wind power projects have been put into production。The bidder must provide a contract that meets the performance requirements of this bidding and a scanned copy of the corresponding production certificate,The scanned copy of the contract must contain at least: the seal page of the contract between the buyer and the seller、The production certification material can be the project production acceptance report or the production completion certificate provided by Party A。

[3] Financial requirements: Financial statements issued by an audit agency or certified public accounting firm from 2021 to 2023 are required;(need to include balance sheet、Cash flow statement、Copy of income statement),If established less than three years,Resulting in the inability to provide the above financial statements,Provide financial statements issued by audit institutions or certified public accounting firms since the company’s establishment;(need to include balance sheet、Cash flow statement、Copy of income statement)。

[4] Credibility requirements: The bidder’s letter of commitment to self-examination of social credibility from January 1, 2021 to the present (stamped with the company’s official seal);The bidder needs to provide the "China Execution Information Disclosure Network" website (http://zxgk when obtaining documents.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty。The tenderer shall impose restrictions on dishonest persons subject to execution who are restricted from participating in bidding activities for engineering construction projects in accordance with laws and regulations。

[5]Qualification requirements for chief supervisory engineer:

(1) The bidder must provide a valid registered supervision engineer qualification certificate of the proposed chief supervision engineer。

(2) Wind power project: Chief supervisory engineer is under 55 years old,Have at least one working experience as a chief seabet online casinoseabet clubsupervisory engineer for wind power project supervision services with a capacity of 100MW and above,The bidder must provide supporting documents proving the performance of the chief supervisory engineer,It can be the contract and the completion acceptance certificate or user certificate of the corresponding project and other stamped materials (the above materials must reflect the name of the project、Chief Supervisory Engineer、Completion/completion time and unit name)。

330kV Booster Station Expansion Project: Chief Supervisory Engineer Age Under 55,Have at least 1 working experience as the chief supervisory engineer of 110kV and above substations,The bidder must provide supporting documents proving the performance of the chief supervisory engineer,It can be the contract and the completion acceptance certificate or user certificate of the corresponding project and other stamped materials (the above materials must reflect the name of the project、Chief Supervisory Engineer、Completion/completion time and unit name)。

(3) The director’s representative shall not replace the director’s permanent presence on site,The director shall not concurrently take on other projects besides this project,The bidder must provide a letter of commitment to meet relevant requirements。

(4) Proof that the director has paid social security for at least three consecutive months within the unit within six months。

[6] Other key personnel requirements:

(1) The wind power project in Area F must be equipped with a full-time deputy chief safety supervisor engineer,Under 55 years old,The proposed deputy chief safety engineer must have a valid registered safety engineer qualification certificate。

(2) The bidder must provide the supervision performance of no less than one wind farm managed by the proposed deputy chief safety supervisory engineer from January 1, 2021 to the bidding deadline,Attach the contract and corresponding user certification materials (can reflect the name of the project、Name of Deputy Safety Director、Commissioning and other contents)。

Note: The qualifications and performance of parent and subsidiary companies are not allowed to be borrowed from each other.

3.2. This project does not accept consortium bids.

4. Obtaining bidding documents

4.1.How to participate in the bidding: Bidding units need to register on the Sunshine Procurement Service Platform,Search for the project after registration and click to bid to participate,For the operation of the bidding unit, please refer to the "Service Center-Operation Guide" on the homepage (register and click on bidding to participate,No need to apply for CA lock)。4.2.Time: 9:00 on July 18, 2024 to 17:00 on July 23, 2024,(Beijing time,Except legal holidays),Information required to obtain documents: ①Business license、Enterprise qualification certificate ② Power of attorney of legal representative and ID card of the authorized person、Proof of social security payment of the unit in the past 3 months ③ Bidder’s social security and tax certificate for any 3 months within 6 months before the deadline for bidding ④ Similar project performance contract and corresponding production certification materials ⑤ Statement of financial status ⑥ Bidder’s social security Credit self-examination commitment letter、"China Execution Information Disclosure Network" website (http://zxgk.court.gov.cn/shixin/) Screenshot of the webpage to check whether the unit is a dishonest person subject to enforcement ⑦ Relevant certification materials required by project personnel ⑧ Bidding document fee remittance voucher ⑨ Bidder information registration form,Customized format,Including bidder’s name、Contact、Contact information、seabet app downloadBasic information such as email address。The bidder shall send a scanned copy seabet betting platformof the original documents or a scanned copy of the official seal (the picture must be clear and legible) (pdf format) to sdzb910@163.com,After successful sending, call the agency for review and confirmation。4.3.Tender document price: 500 yuan/copy,No refund upon sale (only business-to-business transfers accepted,Personal transfers are not accepted,Please note the item number when remitting)。Tender document fee account: Company name: Shandong Tendering Co., Ltd. Account opening bank: Bank of China Jinan Wenhua Road Branch Bank account number: 227305483177 Bank number: 104451038330。4.4.Potential bidders who have not obtained the bidding documents in accordance with the requirements of this announcement shall not participate in the bidding。

5. Submission of bid documents and bid opening

Submission deadline: 09:30 on August 9, 2024;

Submission method and address: Paper document submission;Conference Room on the 2nd Floor, Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

6. Bid opening time and place

Bid opening time: 09:30 on August 9, 2024;

Bid opening location: Conference Room on the 2nd floor, Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

7. Media for publishing announcements

This bidding announcement is also on the China Bidding and Bidding Public Service Platform (http://www.cebpubservice.com/)、Shandong Procurement and Tendering Network (https://www.sdbidding.org.cn/home)、Sunshine Procurement Service Platform (http://www.ygcgfw.com/)、Shandong Development Investment Holding Group Co., Ltd. website (https://www.sdfztz.com/)。

8.Contact information

Tenderer: Baiyin Jingtai Longlu Development New Energy Co., Ltd.
Tenderer’s address: No. 21, Beitan Village, Xiquan Town, Jingtai County, Baiyin City, Gansu Province

Tenderer contact person: Zhang Gong

Tenderer’s contact number: 17616758749

Agency: Shandong Tendering Co., Ltd.

Agent address: No. 13, Wenhua West Road, Lixia District, Jinan City

Agency contact: Manager Liu

Agent contact number: 0531-81917677、15069174047

Agent email: sdzb910@163.com