(Project number: 0627-23101501581)

seabet io

The quantity measurement service project during the construction process of Shandong Development Investment's "Long Electric Power Project in Shandong" new energy project has been approved by the project approval/approval/recording authority,The source of project funds is self-raised funds,The tenderer is Baiyin Jingtai Longlu Development New Energy Co., Ltd.。This project has met the bidding conditions,The current bidding method is public bidding。

2. Project overview and bidding scope

2.1 Project Overview:

"Long Power to Shandong" new energy project planned capacity of 3 million kilowatts,Including 1.8 million kilowatt wind power projects and 1.2 million photovoltaic projects。The overall project location is Tainan、Jingtai North、Development of four areas in Jingyuan and Pingchuan,Among them, the first batch of new energy projects in Baiyin Base will be qualified for grid connection within 2023 as planned。

According to the current progress of the company’s “Long Power to Shandong” new energy project,Consider the number and professional mix of existing personnel in the project management department,To ensure that the project is successfully completed and put into production on time,Need to purchase construction process quantity measurement services,As a supplement to project department management。

The service items of this bidding are:

⑴, Jingtai Area A 400,000 kilowatt wind power project

The total installed capacity of this project is 400MW。This project plans to install 72 units 5.56MW wind turbine,Supporting installation of 72 box-type transformers,This project will build a new 110kV booster station,110kV booster station installs four 150MVA three-phase three-winding power transformers。In this phase, three 150MVA main transformers will be constructed and the installation position of one 150MVA main transformer will be reserved。This station is connected to the 110kV side of Jingtai South 330kV booster station with 2 110kV lines,Through the main transformer of Jingtai South 330kV booster station, it is boosted and then connected to the power grid。110kV electrical main wiring: adopting the form of "one station and two stations",Set two 110kV power distribution devices with single busbar connections in the booster station;The 35kV side of the main transformer adopts single busbar wiring,Each transformer is equipped seabet loginwith a section seabet loginof 35kV busbar on the 35kV side,35kV bus connected to the fan incoming line、Reactive power compensation、Energy storage、Station electricity, etc.;Each main transformer low-voltage side is equipped with one set of ±45MvarSVG reactive power compensation device for each 35kV busbar。

This project is a mountain wind farm,About 80 kilometers of new roads,Renovation and expansion of the road by about 60 kilometers,The excavation volume is about 2.2 million cubic meters。Overhead line 116.7 kilometers。This project is divided into two bidding sections for general contracting (PC) bidding,The contract includes all equipment except the wind turbine tower、Construction and installation project、Other fees (processing、Land acquisition、Grave relocation、Attachment compensation, etc.)。The contract price is in the form of fixed total price + fixed unit price,The booster station has a fixed total price,The rest are fixed unit price settlement methods。The method of payment for progress payment is based on the quantity of work。

The planned construction period of this project is August 2023-June 2024。

⑵, Jingtai Area F 200,000 kilowatt wind power project

The total installed capacity of this project is 200,000 kilowatts,The site is located near the 400,000-kilowatt wind power project in Area A,shares a booster station with it。This project plans to install 36 units5.56MW wind turbine,Supporting installation of 36 box-type transformers。The terrain is similar to the 400,000-kilowatt wind power project in Area A,The project is EPC general contracting,Divided into one bidding section,Progress payment shall be paid according to the quantity of work。

The planned construction period of this project is October 2023-June 2024。

⑶, 330kV substation

The 330kV substation project in Fangcao Village, Luyang Town is located on the east side of the Wuma Expressway in Fangcao Village, Luyang Town, Jingtai County, Gansu Province。The west side of the station site is a rural access road next to the highway,Connected to every village road,The inbound road is directly connected from the access road。The planned land area of ​​the substation is 4.2084 hectares,The land area is about 253.5m,About 166m wide。The substation plans to connect to the new energy installed capacity of about 1200MW。This project plans to install two 360MVA transformers and two 240MVA transformers at the end of the project,330kV final outgoing line 2 times,8 final outgoing lines on the 110kV side。No outlet on the 35kV side,Only reactive power compensation and station power supply equipment。Based on site location and system planning,330kV、110kV all use overhead outlets。Construction scale of this phase: installation of 2 360MVA transformers and 1 240MVA transformer,330kV outgoing line once,110kV outgoing line 4 times,No outlet on the 35kV side,Only reactive power compensation and station power supply equipment。

This project is an EPC general construction contract,The method of payment for progress payment is based on the quantity of work。

The planned construction period of this project is August 2023-January 2024。

⑷、330kV line

The 330kV substation in Fangcao Village, Luyang Town is connected to the Shicheng 330kV substation with one 330kV line。The length of the new line is about 42.8km,Considering the near future、Future wiring method,LGJ-2×630 steel core aluminum stranded wire is used on the Jingtai South 330kV substation side,Shicheng 330kV transformer side adopts LGJ-2×300 steel core aluminum stranded wire。About 10km of the 330kV Shicheng to Yingshuiqiao line is used。The construction method of this section of line is to be determined,Possibly to benefit the old、Build it yourself or find other methods。

This project is an EPC general construction contract,The method of payment for progress payment is based on the quantity of work。

The planned construction period of this project is August 2023-January 2024。

⑸, Lucheng and other 200,000 kilowatt photovoltaic projects

Divided into four projects for implementation,Four projects share a 110kV booster station。The project terrain is piedmont hills,The surface is slightly seabet loginundulating。The project installed a total of about 450,000 550-type monocrystalline double-sided double-glass P-type photovoltaic modules,8600 tons support,896 string inverters,Cable length is about 1800 kilometers,The support foundation is in the form of cast-in-place piles。

This project plans to purchase four PC construction general contractors,The method of payment for progress payment is based on the quantity of work。

The planned construction period of this project is from October 2023 to June 2024 (planned to be implemented in separate projects)。

⑹, Wufo and other 100,000 kilowatt photovoltaic projects

Divided into two projects for implementation,The two projects share a 110kV booster station。The project terrain is piedmont hills,The surface is slightly seabet loginundulating。seabet casino reviewThe project plans to install about 220,000 550-type monocrystalline double-sided double-glass P-type photovoltaic modules (or other forms,To be determined),4300 tons support,398 string inverters,Cable length is about 900 kilometers,The support foundation is in the form of cast-in-place piles。

This project plans to purchase two PC construction general contractors,The method of payment for progress payment is based on the quantity of work。

The start date of this project is to be determined,The construction period is considered to be 6 months,It is planned to have grid connection conditions before September 2025。

⑺、110kV line

This project includes a total of three lines and nine overpass point improvements,For EPC construction general contracting,The method of payment for progress payment is based on the quantity of work。The project content includes equipment fees、Construction and installation fee、Other expenses (demolition、Compensation、Formalities, etc.)。

This project plans to purchase an EPC construction general contractor,The method of payment for progress payment is based on the quantity of work。

The planned construction period of this project is August 2023-January 2024。

①, Temple view line:

One circuit from Sitan North 110kV booster station to Jingtai South 330kV to 110kV line,New single circuit about 28.8km。Conductor 2×JL/G1A-240/30 steel core aluminum stranded wire,One lightning protection line uses OPGW-13-90-2 optical cable,The other one uses 1×19-11.5-1270-B type galvanized steel strand (about 3km of JLB20A-80-7 aluminum-clad steel strand is erected in the Jingtai South 330kV transformation line section)。New tower 95 base,Among them: linear tower 68 base,Corner Tower 27 Base。

②、Lujing Line:

Lucheng 110kV booster station to Jingtai South 330kV to 110kV line once,New single circuit about 12km。Conductor 2×JL/G1A-240/30 steel core aluminum stranded wire,One lightning protection line uses OPGW-13-90-2 optical cable,The other one uses 1×19-11.5-1270-B type galvanized steel strand (about 3km of JLB20A-80-7 aluminum-clad steel strand is erected in the Jingtai South 330kV transformation line section)。New Tower 40 Base,Among them: linear tower 28 base,Corner Tower 12 Base。

③Underground line:

Xiatan 110kV booster station to Jingtai South 330kV to 110kV line second circuit,New single circuit about 3.4+3.1km、Double circuit about 22.6km。Conductor 2×JL/G1A-400/35 steel core aluminum stranded wire,One lightning protection line uses OPGW-13-90-2 optical cable,The other one uses 1×19-11.5-1270-B type galvanized steel strand (about 3km of JLB20A-80-7 aluminum-clad steel strand is erected at the end of Jingtainan 330kV transformer line)。New Tower 101 Base,Among them: linear tower 63 base,Corner Tower 38 Base。

④. Modification of drill-through point:

A total of 9 penetration points and a total of 18 existing towers have been reconstructed。The project crosses the Baotou-Lanzhou Railway many times、Wuma Expressway、Dingwu Expressway, etc.。

2.2 Bidding scope and division of bid sections (packages)

⑴、Tender scope

In the process from project start to full capacity grid connection,Measurement services of engineering quantity/workload of the general construction contract (EPC or PC) involved in the project,Including but not limited to:

1、Progress payment measurement services for general construction contracting contracts。Statistics on the actual amount of work completed by construction units each month,Summarize the progress payments to be made according to the contract requirements。Requires calculation manuscript,Including excel table format、Software form (the software requires the use of Glodon measurement software)。The submitted information and results must be stamped with the cost engineer’s seal and the company’s official seal (the progress payment application form can be stamped with the project seal),Engineering quantity draft specifications can be checked。

2、Measurement services for construction process change visa,Calculate the workload involved in changing visas during construction according to specifications,And use professional terminology to accurately describe it on the visa。

3、According to the construction progress and construction drawing progress,Dynamic adjustment of contract amount,Provide early warning to the owner when there is a large deviation and analyze the reasons。Reasonable prediction of project quantities,Preparation monthly、Quarter、Semi-annual、Annual Fund Plan。

4、Requires registration of migrant workers at different work surfaces (install facial recognition registration equipment,Expenses borne by the construction unit),Regular phone calls to verify the wage payment status of migrant workers,To prevent wage disputes among migrant workers。

5、Other work related to engineering quantity measurement arranged by the construction unit。

Work requirements: Each project is equipped with one person to maintain on a long-term basis (at least three people in total),Professional and reasonable combination,At least one of the on-site personnel in each bid section has the qualification of level two cost engineer (excluding cost engineer) seabet online sports bettingor above,The rest of the personnel must seabet app downloadhave work experience,Meet project requirements。Each project will be on site for more than 22 days per month during the construction process (face-scanning statistics),And obey the arrangements of the construction unit or its representatives。The quotation includes a set of Feishida earthmoving software V16 used by the tenderer.2 (one year usage period,price 3499 yuan),The bidder considers the cost of using the software by himself,The bidder is equipped with GPS high-precision positioning equipment for measuring the amount of earthwork。

⑵, bid segment (package) division

This bidding is divided into one section。This project does not accept consortium bids。

2.3 service period: from project start to full capacity grid connection,But affected by tomb relocation, etc.,The construction period may be changed。Therefore, the bidder will consider the quotation based on the planned construction period + 1 month,The cost can be adjusted when the actual construction period exceeds the planned construction period ±1 month,Every additional (subtracted) month,The added or deducted fee is the quoted monthly unit price*0.8。

2.4 Service location: Baiyin City, Gansu Province where the project is located.

2.5 Service quality requirements: meet current national requirements、Local and industry regulatory requirements,Meet the company system regulations of the construction unit。

3. Bidder qualification requirements

3.1. Bidder qualifications, capabilities and credibility requirements:

[1]Qualification requirements:

(1) Must have independent legal personality of the People’s Republic of China,Have a legal and valid business license。

(2) There has been no fraudulent bidding in the past three years、Severe breach of contract and other bad behaviors,The bidder has no country、Industry、Bad records of the company and its subsidiaries。

[2]Performance requirements: January 1, 2020 to the bidding deadline,The bidder has at least 2 general contracting (PC or EPC or BT) cost consulting performance for wind power projects or photovoltaic projects of 100MW and above。Bidders must provide scanned copies of contracts and corresponding certificates that meet the performance requirements of this bidding,The scanned copy of the contract must contain at least: contract content page、Seals page of both parties to the contract。

【3】Financial requirements: Financial statements issued by an audit agency or certified public accounting firm from 2020 to 2022 (the past three years) are required;(need to include balance sheet、Cash flow statement、Copy of income statement),If established less than three years,Resulting in the inability to provide the above financial statements,Provide financial statements issued by audit institutions or certified public accounting firms since the company’s establishment;(need to include balance sheet、Cash flow statement、Copy of income statement)。

[4] Credibility requirements: The bidder’s commitment to self-examination of social credibility from January 1, 2020 to the present (the format of the self-examination commitment is self-drafted、With official company seal);Bidders need to provide the "China Execution Information Disclosure Network" website (http://zxgk when registering.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty。The tenderer shall impose restrictions on dishonest persons who are restricted from participating in bidding activities for engineering construction projects in accordance with laws and regulations。

【5】Personnel qualification requirements:

(1) The project manager is a first-level cost engineer,Under 55 years old,Have at least one performance in wind power projects or photovoltaic projects with a capacity of 100MW and above。(The supporting material can be the contract page、Finalization form or owner’s description)

(2) The on-site personnel must have at least a second-level cost engineer qualification or above (at least one person is required)。

(3) Project participants are all regular employees of the company,And meet project requirements。

Note: The qualifications and performance of parent and subsidiary companies are not allowed to be borrowed from each other.

3.2. This project does not accept consortium bids.

4. Obtaining bidding documents

Acquisition time: from 09:00 on August 10, 2023 to 17:00 on August 14, 2023

How to obtain:

1、How to participate in the bidding (registration): Bidding units need to seabet sports bettingregister on the Sunshine Procurement seabet app downloadService Platform,Search for the project after registration and register,For the operation of the bidding unit, please refer to the "Service Center-Operation Guide" on the home page (just register and register,No need to apply for CA lock)。

2、Materials required to obtain bidding documents: ①Business license ②Power of attorney of legal representative and authorized person’s ID card ③Similar project performance contract ④Financial status statement ⑤Bidder’s social credit self-examination commitment ⑥"China Execution Information Disclosure Network "Website (http://zxgk.court.gov.cn/shixin/) Web page screenshot ⑦ Project Manager Level 1 Cost Certificate、Social security and performance ⑧ On-site personnel qualification certificate and relevant certification materials required by social security (cost engineer level two or above) ⑨ Cost of construction fee remittance voucher ⑩ Bidder information registration form,Customized format,Including bidder name、Contact、Contact information、Basic information such as email address。The bidder shall send the scanned copy (pdf format) of the above information (in order of serial number) with official seal to sdzb910@163.com,After successful sending, call (15726160669) to notify the agency for review and confirmation。

3、Tender document price: 500.00 yuan/serving,No refund upon sale (only business-to-business transfers accepted,Personal transfers are not accepted,Please note the item number 0627-23101501581 when remitting)。

Tender document fee account:

Company name: Shandong Tendering Co., Ltd.

Account opening bank: Bank of China Jinan Wenhua Road Branch

Bank account number: 227305483177

Line number: 104451038330

4、Potential bidders who have not obtained the bidding documents in accordance with the requirements of this announcement shall not participate in the bidding。

5. Submission of bid documents and bid opening

Submission deadline: 14:00 on August 30, 2023

Submission method and address: Submission of paper documents in the conference room, 2nd floor, Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

6. Bid opening time and place

Submission deadline: 14:00 on August 30, 2023

Submission method: Conference Room, 2nd Floor, Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City

7. Media for publishing announcements

This bidding announcement is also on the China Bidding and Bidding Public Service Platform (http://www.cebpubservice.com/)、Shandong Procurement and Tendering Network (http://www.sdbidding.org.cn)、Sunshine Procurement Service Platform (http://www.ygcgfw.com/)、Shandong Development Investment Holding Group Co., Ltd. website (https://www.sdfztz.com/)。

8.Contact information

Tenderer: Baiyin Jingtai Longlu Development New Energy Co., Ltd.

Tenderer’s address: 8th Floor, Jinwo Kaidi Building, Baiyin District, Baiyin City, Gansu Province

Contact person of the tenderer: Mr. Zhang

Tenderer’s contact number: 17616758749

Tendering agency: Shandong Tendering Co., Ltd.

Address: No. 13, Wenhua West Road, Lixia District, Jinan City

Contact: Li Min

Tel: 15726160669

Email: sdzb910@163.com