1. Bidding conditions

The name of this bidding project is Baiyin Jingtai Longlu Development New Energy Co., Ltd. Jingtai Area B Phase III 100,000 kilowatt photovoltaic project general contracting EPC project,The tenderer is Baiyin Jingtai Longlu Development New Energy Co., Ltd.,The source of funds is self-raised by the enterprise,The bidding agency is Shandong Tendering Co., Ltd.。This project has met the bidding conditions,Now open bidding for this project。

2. Project Overview and Bidding Scope

2.1 Project Overview

Jingtai Area B Phase III 100,000 kilowatt photovoltaic project is located in Zhongquan Town, Jingtai County, Baiyin City, Gansu Province,Rated capacity is 100MW,DC side capacity is 122.2MWp,Content includes photovoltaic module array、Inverter、Box type transformer、Inspection Road,This project is connected to the completed 110kV booster station of Shanfa Ruizhu Second Photovoltaic Power Station through 35kV overhead lines。

2.2 Bid segment (package) division

This bidding is divided into one bidding section.

2.3 Bidding Scope:

Baiyin Jingtai Longlu Development New Energy Co., Ltd. Jingtai Area B Phase III 100,000 kilowatt photovoltaic project general contracting EPC project scope,Mainly including but not limited to:

(1) Equipment procurement scope:

The scope of equipment procurement includes but is not limited to the following: all equipment that meets the installed capacity of this project、Secondary equipment,Also includes corresponding spare parts、Special tools、Instruments, etc.,All equipment and services must meet the technical requirements of smart power stations in the bidding documents。Specific requirements shall be implemented in accordance with the technical specifications of the design institute,The equipment purchased by the bidder must ensure that it meets the requirements for local power grid access。

Photovoltaic modules are purchased by the tenderer,The rest of the equipment and materials are purchased by the bidder。Main variable、Switch cabinet、Reactive power compensation、Ground change、Inverter、Box transformer、cable、Ring main unit, etc. are purchased by the bidders in the bidder's short list,For the detailed list, please see attachment 07 of the bidding document。

Other production schedules including the above equipment、Urgent delivery、Transportation、Pick up、Unlucky (including storage yard,Reverse the delivery location in the photovoltaic module contract to the construction site)、Acceptance of goods、Warehousing, storage, etc.,The bidder is responsible for equipment relocation and storage site coordination and expenses caused by any reason。

The tenderer supervises the manufacture of major equipment,The bidder’s supervision does not relieve the bidder from its responsibility for the supervision and quality control of the purchased equipment。The bidder is responsible for the supervision and inspection of equipment other than the equipment supplied by Party A。Out seabet mobileof consideration for procurement quality,The tenderer has the right to purchase equipment within the scope of the tender、Exercise supervision and decision-making rights over the process and results of service and professional engineering procurement。The tenderer has the right to monitor all equipment within the bidding scope based on the progress of the project。

(2) Construction scope:

Civil construction that meets the grid-connected operation and acceptance of the project、Electrical Installation、Debug、Grid connection、Trial run,Acceptance and defect elimination at each stage of the project,Environmental protection、Safety、Occupational health and other “three simultaneous” related work,Special acceptance of each project,Personnel training and final delivery operations,Quality warranty service during the warranty period,Cooperate with settlement、Completion final accounts audit and all related work。Specifically include but are not limited to the following:

①Construction project: various equipment foundations for booster stations and photovoltaic fields、Steel structure building、Photovoltaic bracket、Wall Fence、Indoor and outdoor water, electricity, heating and weak current projects、Project Greening、Various ancillary facilities projects、Construction and demolition of temporary buildings、Renovation of roads damaged by construction and restoration of vegetation in construction areas、Construction of on-site production and living communication lines and water and power supply (surrounding ecological environment protection during the process、Domestic water source protection and management、Water Conservation、Environmental protection measures guarantee)、Finished product care、Reclamation project (reclamation deposit shall be paid by the contractor、Return)、Environmental protection projects and soil and water conservation projects (meet the relevant requirements for approval and acceptance)。

②Electrical installation project (meeting power grid and preliminary design requirements): installation of all primary and secondary equipment、Debug,Including primary and secondary equipment of booster station、Photovoltaic module installation、Inverter installation、Box transformer installation、Grounding system、Video surveillance system engineering、Centralized control system、Collection line project、Firefighting system、Protection system、Metering system、Scheduling data network and in-station network communication system、Optical power prediction system、Background monitoring system、Power Grid Access System Engineering、All devices mentioned in the access system report approval、Material、All primary and secondary equipment debugging and unit testing of materials and equipment in preliminary design、Overall system debugging、Complete system performance test after grid connection、All equipment signage projects and all electrical equipment installation related work。

③According to the national and green energy company quality acceptance management system,Complete key node acceptance、Phase acceptance and defect elimination work。

④Project completion handover and personnel training、Warranty work within the warranty period。

⑤Complete archives that meet the requirements of the construction unit’s archives management system,And complete the filing and transfer as required。

⑥Others not specified but belong to the construction of this project、Trial run、Acceptance、Transfer、Warranty service during the warranty period、Settlement audit and other related work。All projects before handover、The equipment will be kept and cared for by the winning bidder,Any damage、If lost, the winning bidder will be responsible for repair or replacement,And bear the corresponding expenses。

(3) Survey and design scope: All survey and design of this project,Including but not limited to: geological survey、Hydrology、Micro-site selection、Equipment Technical Specification、Construction drawing design and review、Preparation of as-built drawings;Preparation of a special article on safety facility design;Conduct technical briefing on construction drawings、On-site labor service, etc.。The contractor must design in accordance with the relevant regulations on the construction of photovoltaic power stations of Baiyin Jingtai Longlu Development New Energy Co., Ltd. and meet the requirements。

(4) Scope of procedures:

①、Complete all procedures required for the project,Including but not limited to: the entire construction period of the project and the long-term land acquisition and lease、Grassland、Demolition、Relocation of above-ground and underground lines、Cemetery、Compensation (such as young crop compensation、Forest land compensation、Production reduction compensation、Forest grassland vegetation seabet online casinorestoration fees, etc.)、Reclamation (reclamation deposit shall be paid by the bidder、Return)、Coordination、All fees and procedures involved in surface attachments (land transfer fee for land acquisition for booster station、Except farmland occupation tax and land use tax、Except for long-term leased land in photovoltaic field areas)。Responsible for the procedures for temporary land use for on-site construction and temporary land use at the site、Compensation costs for demolition of above-ground and underground attachments,Processing procedures for highway openings and crossings,Procedures for crossing power and communication lines;Civil Coordination for Approach Roads;Power grid company procedures;The bidder is solely responsible for local coordination during the construction process (not limited to coordination of work interruptions caused by any reason、Local government coordination, etc.)、Facility restoration and other work after construction。

②、Processing of various procedures from the early stage of the project to the project commissioning and operation: real estate certificate、Construction Land Planning Permit、Project Planning Permit、crossing (drilling) administrative license、Access approval procedures、Quality Supervision、Grid connection、Environmental Impact Assessment、Water Conservation、Fire protection and other special acceptance and procedures (obtain relevant documents),And bear the expenses。

③、Technical services related to this project,If designed to cooperate、Site selection review、Factory training、On-site training、Device debugging、Unit trial operation and other electrical equipment warranty services, etc.。Equipment installation、Debug、Test、Inspection and testing required by power grid companies at all levels、Electricity secondary security protection evaluation、Test、Grid-connected trial operation、Eliminate defects、Acceptance,Handle all construction and safety risks related to the project、Third party liability insurance。Complete acceptance and project handover、Related work for the acceptance of archive materials,And all work related to general contracting projects。

For the list of preliminary projects that have been entrusted by the contractor, please see attachment 02 of the bidding document。

(5), tools:

Party B is responsible for purchasing the production operation and maintenance tools and safety tools necessary for equipment operation and maintenance,See attachment 04 for details。

(6) This bidding does not include project supervision services.

(7) Production preparation scope: necessary production tools required for site operation and maintenance、Instrumentation、Insulated tools、Grounding wire facilities and various production preparations。

(8) Quality of the contractor’s general contracting project、Safety、Construction period、Be fully responsible for cost and environmental protection。

(9) All income from the electricity sales of this project belongs to Party A.

(10) Procedures encountered during project construction、Coordination、Payment、Work、Acceptance, etc.,Unless the contract clearly stipulates that Party A is responsible,Regardless of whether it is included in the bidding bill of quantities,All belong to the scope of work of Party B。If the bidder cannot respond to all the requirements of the bidding documents,Discrepancies should be clearly stated in a separate document,Otherwise, regardless of whether the content of the bidding document is consistent with the requirements of the bidding document,It is deemed that the bidder has responded to all requirements of the bidding documents。

For other details, please refer to the employer’s requirements.

2.4 project duration

Start time: before September 30, 2024 (the specific construction period shall be subject to the start date issued by the contractor),Meet the conditions for grid connection before April 25, 2025,Meet full capacity grid connection conditions before May 25, 2025。

3. Bidding conditions

3.1 Bidder qualifications, capabilities and credibility requirements:

[1]Qualification requirements:

①The bidder must be an independent legal person or other organization registered in accordance with the law,Valid supporting documents must be provided,Must have project performance capabilities,And in staff、Equipment、Having the ability to undertake bidding projects in terms of funds and other aspects,Have a good record of paying taxes and social security funds in accordance with the law。

②The bidder should have both ac or the qualifications specified by bc:

a) Engineering design comprehensive qualification Class A、Engineering Survey Comprehensive Qualification Class A、Power engineering construction general contracting qualification level two or above;

b) The bidder should have the first-level seabet mobileor above general contracting qualification for power engineering construction issued by the construction administrative department and the installation (repair) qualification issued by the National Energy Administration.、Trial) Electric Power Facilities Level 1 License。

c) Valid safety production license.

[2] Performance requirements: Bidders should have PC general contracting or EPC general contracting performance for 2 or more ground-mounted photovoltaic projects with a cumulative scale of more than 200,000 kilowatts from January 1, 2021 to the present (time is based on completion acceptance time subject)。The bidder must provide a contract that can prove the performance requirements of this bidding and corresponding project completion certification materials,Contract materials must contain at least: page with seals of both parties to the contract、Contract signing date、Contract scope content and key technical parameters and other information;Proof of project completion should be one of the following certificates: State Electricity Regulatory Commission document、Project Start Handover Signature、Transfer of appraisal certificate、Production certificate、Completion Certificate、Grid connection certificate、Completion Acceptance Report。

[3] Financial requirements provide financial statements issued by an auditing agency or certified public accounting firm from 2021 to 2023;(need to include balance sheet、Cash flow statement、Copy of income statement,Missing any item is considered not provided),If the 2021-2023 audit report or financial statements cannot be provided,Relevant certificates are required if the company has been established for less than three years,Resulting in the inability to provide the above financial statements,Provide financial statements issued by audit institutions or certified public accounting firms since the company’s establishment;(need to include balance sheet、Cash flow statement、Copy of income statement,Missing any item is considered not provided)。

[4] Credibility requirements: The bidder’s social credibility self-examination commitment from January 1, 2021 to the present (stamped with the company’s official seal、Customized format);The bidder needs to provide the "China Execution Information Disclosure Network" website (http://zxgk when obtaining documents.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty。The tenderer shall impose restrictions on dishonest persons who are restricted from participating in bidding activities for engineering construction projects in accordance with laws and regulations。

[5]Qualification requirements for project managers:

(1) The bidder must provide the proposed project manager’s valid registered first-class construction engineer qualification certificate (construction engineering or mechanical and electrical engineering major) or senior engineer title、Valid Class B Safety Production Assessment Certificate。

(2) The proposed project manager must have the performance of at least one PC general contracting or EPC general contracting project manager for photovoltaic projects of 50MW and above,The bidder must provide supporting documents proving the performance of the project manager,It can be a contract or acceptance certificate or user certificate and other stamped materials (the above materials must reflect the name of the project、Project Manager、Completion/commissioning time and unit name)。At the same time, the social security certificate of the project manager who has worked for the bidding unit for the past one year must be provided。

[6] Qualification requirements for the design person in charge (requirements for design-focused bidders):

(1) The bidder must provide a valid survey and design registration practice certificate of the proposed design person in charge。

(2) The design person in charge must have at least one working experience as the design person in charge of photovoltaic projects of 50MW and above,The bidder must provide supporting documents that can prove the performance of the person in charge of the design,It can be a contract or acceptance certificate or user certificate and other stamped materials (the above materials must reflect the name of the project、Design person in charge、Completion/commissioning time and unit name)。

[7] Qualification requirements for the construction person in charge (requirements for bidders focusing on construction):

(1) The bidder must provide the proposed construction responsible person with a valid first-class registered construction engineer qualification certificate (construction engineering or mechanical and electrical engineering major) and a valid Class B safety production assessment certificate。

(2) The construction leader must have at least one experience as the construction leader or project manager of a photovoltaic project of 50MW or above,The bidder must provide supporting documents that can prove the performance of the person in charge of the construction,It can be a contract or acceptance certificate or user certificate and other stamped materials (need to include the name of the project、Construction manager、Completion/commissioning time and unit name)。

[7] Project management organization and personnel: The bidder must provide the valid "Safety Management Personnel seabet ioQualification Certificate" C certificate of the proposed safety person in charge。

[8] Requirements for purchasing goods: The procurement of major equipment and materials is strictly carried out in accordance with the short list of the bidding documents,Submit the procurement plan and procurement results to the contractor for review and approval。

3.2 This project does not accept consortium bids.

4. Obtaining bidding documents

Time: 09:00 on September 5, 2024 to 17:00 on September 11, 2024

4.1 Bidding participation method: Bidding units need to register on the Sunshine Procurement Service Platform,Search for this project after registration and click to bid to participate,For the operation of the bidding unit, please refer to the "Service Center-Operation Guide" on the homepage (register and click on bidding to participate,No need to apply for CA lock)。4.2 Information required to obtain documents: ①Business license、Qualification Certificate、The bidder’s social security and tax payment certificate for any three months from March 2024 to the present ②Authorization letter of legal representative and ID card of the authorized person、Proof of social security payment of the unit in the past 3 months ③Performance contract and corresponding project completion certification materials ④Financial status statement ⑤Bidder's credibility self-examination commitment and the "China Execution Information Disclosure Network" website (http://zxgk.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty ⑥Personnel qualification certificate and relevant certification materials required by personnel ⑦Tender document fee remittance voucher ⑧Bidder information registration form,Customized format,Including bidder’s name、Contact、Contact information、Basic information such as email address。The bidder shall send a scanned copy of the original documents above (the picture must be clear and legible) (pdf format) to sdzb910@163.com,After successful sending, call the agency for review and confirmation。4.3 Bidding document price: 750 yuan/copy,No refund upon sale (only business-to-business transfers accepted,Personal transfers are not accepted,Please note the item number when remitting)。Tender document expense account: Company name: Shandong Tendering Co., Ltd.;Account opening bank: Bank of China Jinan Wenhua Road Branch;Bank account number: 227305483177;Line number: 104451038330。4.4Potential bidders who have not obtained the bidding documents in accordance with the requirements of this announcement shall not participate in the bidding。

5. Submission of bid documents

Submission deadline: 14:00 on September 29, 2024 (Beijing time);

Submission method: Conference Room on the second floor of Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

6. Bid opening time and place

Bid opening time: 14:00 on September 29, 2024 (Beijing time);

Bid opening location: Conference Room on the second floor of Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

7. Media for publishing announcements

This bidding announcement is also on the China Bidding and Bidding Public Service Platform (http://www.cebpubservice.com/)、Shandong Procurement and Tendering Network (http://www.sdbidding.org.cn)、Sunshine Procurement Service Platform (http://www.ygcgfw.com/)、Shandong Development Investment Holding Group Co., Ltd. website (https://www.sdfztz.com/)。

8.Contact information

Tenderer: Baiyin Jingtai Longlu Development New Energy Co., Ltd.

Tenderer’s address: 8th Floor, Jinwo Kaidi Building, Baiyin District, Baiyin City, Gansu Province

Tenderer contact person: Manager Zhang

Tenderer’s contact number: 17616758749

Agency: Shandong Tendering Co., Ltd.

Agent address: No. 13, Wenhua West Road, Lixia District, Jinan City

Agency contact: Manager Liu

Agent contact number: 0531-81917677、15069174047

Agent email: sdzb910@163.com