1.Tender conditions

The name of this bidding project is: Baiyin Development Investment New Energy Co., Ltd. (Pingchuan) Area B 200,000 kilowatt wind power project construction general contracting (PC) project,Project bidding number is: 0627-24102072032,The tenderer is: Baiyin Development Investment New Energy Co., Ltd.,The project unit is: Baiyin Development Investment New Energy Co., Ltd.,The source of funds is enterprise self-raising and loans。The bidding agency is Shandong Tendering Co., Ltd.。This project has met the bidding conditions,Now inviting bids for this project。

2. Project Overview and Bidding Scope

2.1 Project Overview, Bidding Scope and Bid Section (Package) Division

2.1.1 Project Overview:

This bidding project is the 200,000-kilowatt wind power project in Area B of Baiyin Development Investment New Energy Co., Ltd. (Pingchuan),Includes one wind farm site area。The project is located in Pingchuan District, Baiyin City, Gansu Province。The straight-line distance from the southeast of the wind farm center to the center of Pingchuan District is about 10.5km,The booster station is about 8 meters away from the center of the wind farm.About 5km,The wind farm is in a mountainous area,There is National Highway G109 on the west side of the wind farm、G6 high-speed passing,Good transportation conditions。The installed capacity is 200MW,Planned to install 32 single machines with a capacity of 6.25MW、Wind turbine with hub height 120m。There are many built wind power project roads around the site that can reach the site,External transportation is more convenient,This project will build a new 110kV booster station,The wind turbine is connected to the 35kV busbar on the low-voltage side of the newly built main transformer through 8-circuit collector lines。After being boosted by the main transformer, it is sent to the power grid through a 110kV line。110kV electrical main wiring: single busbar wiring form。35kV electrical main wiring: The 35kV side of the main transformer adopts single busbar wiring form,Each transformer is equipped with a section of 35kV busbar on the 35kV side,Each 35kV bus section is connected to the fan incoming line、Reactive power compensation、Station electricity, etc.。Each main transformer low-voltage side 35kV busbar is equipped with a set of ±30MvarSVG reactive power compensation device。

2.1.2 Bid segment division:

This project is divided into two bidding sections:

1.png

Both bids for this project were not successful.

2.1.3 Bidding Scope:

Bid Section 1: Baiyin Development Investment New Energy Co., Ltd. (Pingchuan) Area B 200,000 kilowatt wind power project construction general contracting (PC) project (Bid Section 1),Mainly including but not limited to the following:

1. Equipment and material procurement:

1.All equipment and materials that meet the installation requirements of this section of this project,Including but not limited to: box-type transformer、cable、All equipment and materials for collector lines and output lines (including tower materials、Goldware、Wire、Insulator、Attachment、Optical cable, etc.),Main transformer in booster station、Construction transformer、Power distribution device、Reactive power compensation、Switch cabinet、Electrical secondary equipment (including comprehensive automation、Network-related equipment expansion、Communication Equipment、Remote control system、Security monitoring equipment、Wind power forecast、Boost station video surveillance and fire alarm system expansion, etc.)、Centralized control interface and channel reservation,Material(Server、Switch、Firewall、Router、Longitudinal encryption device (including fans, etc.) and corresponding spare parts、Special tools、All software and hardware equipment such as instruments and meters and corresponding technical services,Firefighting facilities,330kV peer station new construction and reconstruction and expansion related equipment,Various equipment, materials and services that meet the technical requirements of smart wind farms in the bidding documents,And supervision of equipment within the procurement scope、Urgent delivery、Transportation、Pick up、Unfavorable shipment (including yard charges)、Acceptance of goods (including third-party inspection required by specifications)、Warehousing, etc.。If the tenderer provides a recommended purchase list, the bidder shall purchase from the tenderer's recommended list,Included into total bid price。Equipment procurement should be strictly carried out in accordance with the technical specifications and recommendation list provided by the tenderer。The equipment purchased by the bidder must ensure that it meets the requirements of local power grid access。

2.Supply equipment: wind turbines、Tower,The equipment supplied by A is not included in the total contract price;

3.Including the production schedule of the above equipment、Urgent delivery、Transportation、Pick up、Unlucky (including storage yard)、Acceptance of goods、Warehousing, storage, etc. (The equipment purchased by the contractor is also entrusted to the contractor for production scheduling、Expediting goods、Receive goods、Keeping、Full process control including bad luck),The contractor is responsible for equipment relocation and storage site coordination and expenses caused by any reason。

4.The bidder arranges for the supply of wind turbines、Supervision and inspection of equipment outside the tower。Out of consideration for purchasing quality,The tenderer has the right to purchase equipment within the scope of the tender、Exercise supervision and decision-making rights over the process and results of service and professional engineering procurement。The tenderer has the right to supply all equipment within the bidding scope based on the progress of the project。

5.All A-supplied equipment and all equipment within the bidding scope of this project、Transportation of secondary equipment、Loading and unloading、Installation and Debugging、Keeping、The bidder shall be responsible for the second bad luck。

6.Construction unit before equipment procurement、The supervision unit will review the construction drawings and technical specifications,Only after the review is correct, the general contractor can proceed with bidding, procurement and construction。The bidder must be comprehensive、Comprehensive consideration of quotation。

7.Bidders should consider the period and before and after major national, provincial and municipal events,Making and transporting major equipment,The bidder shall make the lead time for large equipment transportation according to the overall construction period requirements of the bidder。

8.Above equipment、Material、Spare parts and other technical services、Provision of performance testing and related technical information, etc.。

2. Project construction:

Civil construction that meets the grid-connected operation and acceptance of the project、Wind turbine installation、Electrical installation、Debug、Connected to the grid、Trial run,Acceptance and defect elimination at each stage of the project,Water Conservation、Environmental protection、Safety、Occupational health and other “three simultaneous” and other related work,Special acceptance of each project,Personnel training and final delivery operations,Quality warranty service during the warranty period,Cooperate with settlement、Completion final accounts audit and all related work。Specifically include but are not limited to the following:

1.Civil works: including leveling and earthwork works within the booster station、Road Engineering、Water Conservation and Greening Project、Environmental Protection Project、Water supply and drainage project、Cable trench project、Line Basics、Ancillary facilities engineering、All civil construction related work in the bidding section such as various equipment foundation projects。

2.Electrical installation work: all primary and secondary equipment installation、Debug,includes、Box transformer installation project、Cable Engineering、Grounding System Engineering、Video Surveillance System Engineering、Collection line project、Wind power prediction system、Monitoring background monitoring system、Reserved interfaces and channels for centralized control center、All equipment debugging and unit testing、Overall system debugging、Handover test and acceptance test of the complete system performance test equipment after grid connection、All engineering equipment、Facility、Environmental signage、Production of safety signs、Installation and other related work。

3.The bidder follows Gansu Province’s design standards for wind power project vegetation restoration operations、Vegetation Restoration Plan Report of this Project、Land Reclamation Plan、Environmental protection、Requirements for Soil and Water Conservation Approval Plan,Implement environmental protection、Three simultaneous water and water conservation、Comprehensive land utilization work,The required fees should be fully included in the bid quotation。Under construction,Responsible for ecological environment protection within the construction scope、Domestic water source protection,Take necessary water conservation、Environmental protection measures,Rucao Square、Spreading grass seeds and covering with green net,After the construction is completed, he is responsible for completing the repair work of all environmental impacts such as soil erosion or vegetation damage within the construction scope,Complete vegetation restoration and planting within and around the construction area,The vegetation restoration and greening planting and maintenance period is two years,Finally ensure that the survival rate is not lower than the water conservation approval requirements,And ensure that the project finally passes environmental protection、Soil and water conservation acceptance requirements,All required costs are included in the bid quotation,Results in forestry due to reasons of the bidder、Land、Water Conservation、Environmental protection、Criminal administrative penalties from cultural relics and other related departments,The consequences and related handling and coordination shall be borne by the bidder,The bidder shall bear the relevant costs;The bidder needs to evaluate the current situation of the site before starting work,If the bidder fails to carry out construction in accordance with the requirements, causing damage to water, soil and vegetation beyond the project itself,The resulting costs shall be borne by the bidder,And the tenderer has the right to punish the bidder,The bidder needs to bear the penalties, fines, etc. and administrative criminal penalties incurred by the local government on the bidder。

4.Various construction measures during the construction period,Such as construction precipitation、Drainage、Winter rainy season、High temperature construction, etc.,Included in each construction list item quotation。

5.Applying for various insurances,Including but not limited to construction personnel employer’s liability insurance、Accident insurance、Equipment and material transportation insurance、Construction Equipment Insurance、Safety Production Liability Insurance、And other insurance required by local regulatory authorities、Policy insurance required by national laws and regulations, etc.,Included in bid price,Do not list separately。

6.According to the latest system of project quality acceptance management of the tenderer,Complete key node acceptance、Phase acceptance and defect elimination work。

7.According to relevant standards、Collection of specifications and contract provisions、Organizing all archives during the construction process,Responsible for organizing and transferring the files to the tenderer’s file management department (the information must be organized in accordance seabet casino reviewwith the latest regulations seabet app downloadon the tenderer’s information management,Transfer files that meet the requirements of the tenderer,And complete the arrangement on schedule、Transfer and archive)。

8.Others not specified but belong to the construction of this project、Trial run、Acceptance、Transfer、Warranty service during the warranty period、Related work such as settlement auditing。All projects before handover、The equipment will be kept and cared for by the winning bidder,Any damage、If lost, the winning bidder will be responsible for repair or replacement,And bear the corresponding expenses。

9.The bidder must strictly implement the various rules and regulations issued by the tenderer and the tenderer’s superior unit during the construction process,Such as "New Energy Power Generation Enterprise Safety Visualization Standard Management Manual"、"Measures for the Management of Safety Video Monitoring of New Energy Construction Projects"、"Wind Farm Safety and Civilized Construction Manual"、"Standardized Atlas of Safe and Civilized Construction of New Energy Engineering Construction"、"New Energy Engineering Construction Safety Standardization Management Manual"、"Wind Power Station Project Engineering Acceptance Management Regulations" and other related documents (if there are new regulations issued above,Follow the new regulations),Meet the relevant requirements of the above documents,And the relevant costs are included in the total bid price。

10.Installation, debugging and trial operation project of all equipment、Wind power forecast、35kV collector line construction project (crossing,Including railway、Highway、National Highway、Provincial Road、County Road、Various situations such as rural roads and overhead lines)、New construction and installation project of 1 110kV booster station、Spanning (crossing) involved in the transportation of large equipment,Including railway、Highway、National Highway、Provincial Road、County Road、Various situations such as rural roads and overhead lines)、Relocation line、Demolition、Coordination, etc.,Fire protection engineering、Grounding works and ancillary works、Construction of on-site communication engineering and water and power supply (surrounding ecological environment protection during the process、Domestic water source protection and management、Water Conservation、Environmental protection measures guarantee)、Finished product care、Green vegetation restoration project after completion of the project、Environmental Protection Project、Soil and water conservation project (meeting relevant requirements for approval and acceptance),Domestic water and electricity、Coordination of land acquisition and various coordination during construction、Acceptance (including files、Environmental protection、Water Conservation、Firefighting、Safety、Measurement、Occupational Health、Quality supervision and other completion acceptance),And finally deliver the whole process contracting of grid-connected power generation in accordance with the requirements of the contractor。The bidder’s quotation for this project comprehensively considers winter treatment costs and measures。

11.The transmission line project includes the 110kV booster station gantry (line side) to the 330kV substation 110kV gantry (line side),Including the last wire insulators on both sides、Goldware、Wire,Not including lower drainage line、T-type wire clamp procurement and construction。The 330KV substation side communication optical cable is led from the ground pole to the 110kV booster station optical cable connection box (the connection box is included in this contract),Optical fiber material procurement and laying production under the outlet structure、Light board、Ethernet board system board procurement、Access,Installation and debugging work。Bidders need to consider this related cost when bidding,No further consideration after winning the bid。

12.Corridor for line construction、Roads and Transportation、Issues such as land compensation,Bidders shall consider at their own discretion,The cost is included in the bid price。

13.The contractor is solely responsible for local coordination during the construction process (not limited to work interruption caused by any reason、Local government coordination, etc.),The cost is included in the bid price。

14.Fan、Box transformer and hoisting platform within 50mx60m range、Within 6 meters wide of maintenance road、Compensation for land acquisition within 1 mu of each base tower of the collector line and within the booster station,Land acquisition coordination and other temporary land use、Compensation expenses、The contractor is responsible for all formalities and other work。

15.Contractors should fully consider construction disturbance、Crane transition、Line Corridor、Expansion of maintenance road、Road Repair、Compensation for temporary occupation such as opening the fence and opening the door,The required fees should be included in the bid quotation。

16.The contractor is responsible for environmental protection、Land reclamation and vegetation restoration work for soil and water conservation acceptance,The required fees should be fully included in the bid quotation。

17.The contractor is responsible for the grid connection acceptance stage of the project and the standardization after completion、Refinement (identification、flag、Signage) and other related work,The cost is included in the bid price。

18.Quality of general contracting projects by contractors、Safety、Construction period、Be fully responsible for cost and environmental protection。The construction site of this bidding is a smart construction site,Configuring real-time monitoring system at construction site,Monitoring equipment is purchased by the contractor,And use BIM technology to establish a three-dimensional model of the entire wind power project,The bidder fully considers this cost when bidding (see the attachment for specific configuration standards: Project Smart Site Construction Plan)

The contractor of the winning bid section 2 completed the electrical installation of the wind turbine and completed the cable laying in the tower and connected it to the frequency conversion cabinet at the bottom of the tower. The converter was submitted to the bid section 1 after being accepted by the contractor and the supervision unit as meeting the requirements and completed from 32 Box-type transformer installation (including power cable laying and installation from the fan foundation to the low-voltage side of the box-type transformer,All remaining work from the high voltage side of the box transformer to the laying and installation of power cables for 35kV overhead lines。Bidders of Bid Section 1 need to consider the related costs of this part when bidding and quoting,No further consideration after winning the bid。(Bid Section 2 is responsible for the foundation construction of box transformer)

三、Procedures to be processed (the bidder shall set it according to the project conditions,The following is for reference),Including but not limited to the following:

①All temporarily occupied forest land during the entire project、Land、Grassland、Demolition、Cemetery、Compensation、Coordination、The bidder is responsible for all costs and procedures involved in surface attachments (except farmland occupation tax and land use tax);The long-term land lease procedures and related coordination costs shall be handled and borne by the bidder,Long-term land lease fees shall be borne by the tenderer。

② Various procedures from the early stage of the project to the project put into operation (such as: construction permit,Connected to the grid、Water permit, etc.),Environmental protection、Relocation line、Water Conservation、Meteorology (Lightning Protection)、Energy saving、Occupational Health、Earthquake safety evaluation、Firefighting、Safety、Quality Supervision、Special acceptance and procedures for grid connection and other special procedures (obtain relevant documents),And due to government systems、All fees required by the power grid system policy。The bidder coordinates the application for construction land approval letter、Land planning permit、Project Planning Permit、Real estate certificate, etc. (provide file information to the tenderer、Data and other related files)。

The bidder follows environmental protection、Requirements for Soil and Water Conservation Approval Plan,Complete environmental protection、Water conservation construction、Monitoring、Review and Acceptance,Responsible for the repair of all environmental impacts such as soil erosion or vegetation damage caused during the construction process,And complete land reclamation and vegetation restoration work and meet environmental protection requirements、Soil and water conservation acceptance requirements,Implement the three simultaneous tasks of environmental protection, water conservation and water conservation,The required fees should be fully included in the bid quotation。In principle, fixed unit price bidding is based on bill of quantities,Settlement based on the actual amount of work incurred;Requires an assessment of the current status of the site before starting work,If the contractor fails to perform construction in accordance with the requirements, causing damage to water, soil and vegetation beyond the project itself,The resulting costs shall be borne by the contractor and the contracting party has the right to impose penalties,The contractor needs to bear the penalties, fines and other expenses incurred by the local government against the owner。

③Technical services related to this project,If designed together、Micro-site selection review、Factory training、On-site training、Device debugging、Unit trial operation, other electrical equipment warranty period, two-year warranty service, etc.。Application from power grid company、Plan review、Complete all procedures including acceptance;Signing and coordinating power purchase and sale contracts and grid-connected dispatch agreements with State Grid and related companies;Secondary security and grade protection evaluation、Filing procedures;Complete the project lightning protection grounding test in accordance with the requirements of the local meteorological department,Obtain approval document。Equipment installation、Debug、Test、Inspection and testing required by power grid companies at all levels、Host reinforcement、Electric secondary security protection evaluation (switching station、Boost station)、Test、Grid-connected trial operation、Eliminate defects、Acceptance,Process various types of insurance related to the project。Complete acceptance and project handover、Related work on the acceptance of archive materials,And all work related to general contracting projects。

④Responsible for handling lifting equipment safety filing and other related procedures with the local special equipment supervision and management department,And bear corresponding responsibilities;According to relevant standards、Collection of specifications and contract provisions、Organizing all archives during the construction process,Responsible for organizing and transferring owner’s files to the management department;Responsible for coordinating local relations,Protect、Improve construction environment,Pay various mortgage deposits and insurance,We shall bear corresponding responsibilities and fines for related disputes caused by construction reasons;Responsible for coordinating local civil relations during the construction process,The cost is included in the bid price。

⑤The contractor is responsible for connecting to the power grid,Collect project progress and technical information of power grid transmission and transformation supporting projects,Supervise and track its construction progress。

⑥Complete the project acceptance in accordance with the relevant requirements of Gansu Power Grid Company、Start coordination work and various procedures,Complete the registration of the project power quality supervision station and timely organize and coordinate the supervision and acceptance work at each stage;Cooperate with the debugging required to access the contracting party’s centralized control center、Trial operation and other related work; 

⑦ All civil work on site、Local coordination,Civil、All expenses incurred in handling local relations。

⑧Be responsible for handling the above procedures (including costs related to temporary land use、Report preparation fee、Assessment fee、Conference fees, etc.)、Acceptance、All expenses incurred in the process of handling civil relations (land lease expenses、The land reclamation deposit shall be borne by the contractor),If the construction period is delayed due to the bidder's failure to complete relevant procedures in time、Criminal、All administrative penalties and fines shall be borne by the bidder。

⑨Cooperate in providing relevant information and review and acceptance work. 

For details, please refer to the drawings and bill of quantities。For quality reasons,The tenderer has the right to purchase equipment and materials within the scope of the tender、Exercise supervision and veto rights over the process and results of service and professional engineering procurement。 

In case of land rent issue,Resulting in an increase or decrease in the installed capacity,Final settlement will be based on actual installed capacity;If the construction period is extended,In the end, only the construction period was postponed,Bidders are requested to fully consider and prepare construction organization and response measures,Increased costs caused by work delays and shutdowns are included in the bid quotation。

Anyway,The contractor is responsible for power generation from the date of winning the bid until the project is connected to the grid、Handling of policy procedures for the entire completion acceptance process (including but not limited to: power grid、Government、Industry、Various procedures required by the group)。Among them,After the bid deadline,Equipments added due to new policies and new requirements on the power grid、Changes in services and project quantities,Both parties will issue separate visas after approval by the contractor。The contractor seabet app downloadmust fully consider other policy seabet appprocedures and expenses incurred,Relevant costs are all included in the bid quotation。

Because this project is divided into two bids,for fast、Perform the above procedures efficiently,When the entire project needs to be uniformly oriented to the government or regulatory agency (safety supervision、When completing procedures for quality supervision, etc.,The contractor of bid section 1 will take the lead in handling the process,Every contractor of Bid Section 2 cooperates with the specific work;When the entire project needs to go through the grid connection procedures for the power grid,The contractor of bid section 1 will take the lead in handling the process,Every contractor of Bid Section 2 cooperates with the specific work。The processing fee shall be borne by the contractor who takes the lead in the processing。When the procedures for each bidding section do not involve other bidding sections or can be handled independently,Do it yourself and bear the cost。For details, please refer to the quotation list and bidding document attachments for division instructions。

Any form of punishment due to procedural issues in engineering construction projects,The contractors of each bid section shall bear the responsibility。

4. Tools:

The contractor is responsible for purchasing the production operation and maintenance tools necessary for equipment operation and maintenance、Spare parts,Subject to the final approval of the contractor。The production preparation tools listed in the list of production preparation tools (see attachment for details) are all purchased from bid section 1,And bear the corresponding expenses。

5. Other work scope:

Including but not limited to: Project data file organization、Special acceptance of transfer and files,All necessary works are eliminated、Material、Spare parts、Special tools for production safety、Consumables and related technical information and personnel training,Various meetings during the construction period,Project data includes but is not limited to process data、Completion Information。

The contractor is responsible for power generation from the date of winning the bid until the project is connected to the grid、Handling of policy procedures for the entire completion acceptance process (including but not limited to: power grid、Government、Various procedures required by the industry)。Among them,After the bid deadline,Equipments added due to new policies and new requirements on the power grid、Changes in services and project quantities,Both parties will issue separate visas after approval by the contractor。The contractor seabet app downloadmust fully consider other policy seabet appprocedures and expenses incurred,Relevant costs are all included in the bid quotation。

This bidding does not include project supervision, survey and design.

Contractor’s quality of general contracting projects、Safety、Construction period、Be fully responsible for cost and environmental protection。

All income from the electricity sales of this project belongs to Party A.

Procedures encountered during project construction、Coordination、Payment、Work、Acceptance, etc.,Unless the contract clearly stipulates that Party A is responsible,Regardless of whether it is included in the bidding bill of quantities,All belong to the scope of work of Party B。If the bidder cannot respond to all the requirements of the bidding documents,Differences should be clearly stated in a separate document,Otherwise, regardless of whether the content of the bidding document is consistent with the requirements of the bidding document,The bidder shall be deemed to have responded to all requirements of the bidding documents。

Main changes in the defect liability period of this project、GIS、Main power transformation and distribution equipment such as reactive power compensation、Protective equipment、Comprehensive self-system、Communication equipment and accessories for two years,Others are 1 year。 


Bid Section 2: Baiyin Development Investment New Energy Co., Ltd. (Pingchuan) Area B 200,000 kilowatt wind power project construction general contracting (PC) project (Second Bid Section),Mainly including but not limited to the following:

1. Equipment and material procurement:

1.All equipment and materials that meet the installation requirements of this section of this project,Including but not limited to: wind farm video surveillance and fire alarm system expansion, etc.)、Centralized control interface and channel reservation,Material(Server、Switch、Firewall、Router、Longitudinal encryption device (including fans, etc.) and corresponding spare parts、Special tools、All software and hardware equipment such as instruments and meters and corresponding technical services,Firefighting facilities,Various equipment, materials and services that meet the technical requirements of smart wind farms in the bidding documents,And supervision of equipment within the procurement scope、Urgent delivery、Transportation、Pick up、Unfavorable shipment (including yard charges)、Acceptance of goods (including third-party inspection required by specifications)、Warehousing, etc.。If the tenderer provides a recommended purchase list, the bidder shall purchase from the tenderer's recommended list,Included into total bid price。Equipment procurement should be strictly carried out in accordance with the technical specifications and recommendation list provided by the tenderer。The equipment purchased by the bidder must ensure that it meets the requirements of local power grid access。

2.Supply equipment: wind turbines、Tower,The equipment supplied by A is not included in the total contract price;

3.Including the production schedule of the above equipment、Urgent delivery、Transportation、Pick up、Unlucky (including storage yard)、Acceptance of goods、Warehousing, storage, etc. (The equipment purchased by the contractor is also entrusted to the contractor for production scheduling、Expediting goods、Receive goods、Keeping、Full process control including bad luck),The contractor is responsible for equipment relocation and storage site coordination and expenses caused by any reason。

4.The bidder arranges for the supply of wind turbines、Supervision and inspection of equipment outside the tower。Out of consideration for purchasing quality,The tenderer has the right to purchase equipment within the scope of the tender、Exercise supervision and decision-making rights over the process and results of service and professional engineering procurement。The tenderer has the right to supply all equipment within the bidding scope based on the progress of the project。

5.All A-supplied equipment and all equipment within the bidding scope of this project、Transportation of secondary equipment、Loading and unloading、Installation and Debugging、Keeping、The bidder shall be responsible for the second bad luck。

6.Construction unit before equipment procurement、The supervision unit will review the construction drawings and technical specifications,Only after the review is correct, the general contractor can proceed with bidding, procurement and construction。The bidder must be comprehensive、Comprehensive consideration of quotation。

7.Bidders should consider the period and before and after major national, provincial and municipal events,Making and transporting major equipment,The bidder shall make the lead time for large equipment transportation according to the overall construction period requirements of the bidder。

8.Above equipment、Material、Spare parts and other technical services、Provision of performance testing and related technical information, etc.。

2. Project construction:

Civil construction that meets the grid-connected operation and acceptance of the project、Wind turbine installation、Electrical installation、Debug、Connected to the grid、Trial run,Acceptance and defect elimination at each stage of the project,Water Conservation、Environmental protection、Safety、Occupational health and other “three simultaneous” and other related work,Special acceptance of each project,Personnel training and final delivery operations,Quality warranty service during the warranty period,Cooperate with settlement、Completion final accounts audit and all related work。Specifically include but are not limited to the following:

1.Civil works: including leveling and earthwork works within the wind farm、Road works (including on-site roads,Including new roads and repairs of old roads)、Fan and box transformer foundation project、Grounding Project、Water Conservation and Greening Project、Environmental Protection Project、Water supply and drainage project、Cable trench project、All civil construction related work including ancillary facilities engineering。

2.Electrical installation engineering: Fan electrical installation,Installation of all primary and secondary equipment in the fan、Debug,Includes cable work、Grounding System Engineering、Video Surveillance System Engineering、Wind power prediction system、Monitoring background monitoring system、Reserved interfaces and channels for centralized control center、Overall system debugging、Handover test and acceptance test of the complete system performance test equipment after grid connection、All engineering equipment、Facility、Environmental signage、Production of safety signs、Installation and other related work。

3.The bidder follows Gansu Province’s design standards for wind power project vegetation restoration operations、Vegetation Restoration Plan Report of this Project、Land Reclamation Plan、Environmental protection、Requirements for Soil and Water Conservation Approval Plan,Implement environmental protection、Three simultaneous water and water conservation、Comprehensive land utilization work,The required fees should be fully included in the bid quotation。Under construction,Responsible for ecological environment protection within the construction scope、Domestic water source protection,Take necessary water conservation、Environmental protection measures,Rucao Square、Spreading grass seeds and covering with green net,After the construction is completed, he is responsible for completing the repair work of all environmental impacts such as soil erosion or vegetation damage within the construction scope,Complete vegetation restoration and planting within and around the construction area,The vegetation restoration and greening planting and maintenance period is two years,Finally ensure that the survival rate is not lower than the water conservation approval requirements,And ensure that the project finally passes environmental protection、Soil and water conservation acceptance requirements,All required costs are included in the bid quotation,Results in forestry due to reasons of the bidder、Land、Water Conservation、Environmental protection、Criminal administrative penalties from cultural relics and other related departments,The consequences and related handling and coordination shall be borne by the bidder,The bidder shall bear the relevant costs;The bidder needs to evaluate the current situation of the site before starting work,If the bidder fails to carry out construction in accordance with the requirements, causing damage to water, soil and vegetation beyond the project itself,The resulting costs shall be borne by the bidder,And the tenderer has the right to punish the bidder,The bidder needs to bear the penalties, fines, etc. and administrative criminal penalties incurred by the local government on the bidder。

4.Various construction measures during the construction period,Such as construction precipitation、Drainage、Winter rainy season、High temperature construction, etc.,Included in each construction list item quotation。

5.Applying for various insurances,Including but not limited to construction personnel employer’s liability insurance、Accident insurance、Equipment and material transportation insurance、Construction Equipment Insurance、Safety Production Liability Insurance、And other insurance required by local regulatory authorities、Policy insurance required by national laws and regulations, etc.,Included in bid price,Do not list separately。

6.According to the latest system of project quality acceptance management of the tenderer,Complete key node acceptance、Phase acceptance and defect elimination work。

7.According to relevant standards、Collection of specifications and contract provisions、Organizing all archives during the construction process,Responsible for organizing and transferring the files to the tenderer’s file management department (the information must be organized in accordance seabet casino reviewwith the latest regulations seabet app downloadon the tenderer’s information management,Transfer files that meet the requirements of the tenderer,And complete the arrangement on schedule、Transfer and archive)。

8.Others not specified but belong to the construction of this project、Trial run、Acceptance、Transfer、Warranty service during the warranty period、Related work such as settlement auditing。All projects before handover、The equipment will be kept and cared for by the winning bidder,Any damage、If lost, the winning bidder will be responsible for repair or replacement,And bear the corresponding expenses。

9.The bidder must strictly implement the various rules and regulations issued by the tenderer and the tenderer’s superior unit during the construction process,Such as "New Energy Power Generation Enterprise Safety Visualization Standard Management Manual"、"Measures for the Management of Safety Video Monitoring of New Energy Construction Projects"、"Wind Farm Safety and Civilized Construction Manual"、"Standardized Atlas of Safe and Civilized Construction of New Energy Engineering Construction"、"New Energy Engineering Construction Safety Standardization Management Manual"、"Wind Power Station Project Engineering Acceptance Management Regulations" and other related documents (if there are new regulations issued above,Follow the new regulations),Meet the relevant requirements of the above documents,And the relevant costs are included in the total bid price。

10.Road works (including approach roads、Roads within the venue、Inbound road,Including new roads and repairs of old roads)、Fan and box transformer foundation project、Installation, commissioning and trial operation engineering of all equipment in the bid section (including fans、Tower)、Wind power forecast、Spanning (crossing) involved in the transportation of large equipment,Including railway、Highway、National Highway、Provincial Road、County Road、Various situations such as rural roads and overhead lines)、Relocation line、Demolition、Coordination, etc.,Fire protection engineering、Grounding works and ancillary works、Construction of on-site communication engineering and water and power supply (surrounding ecological environment protection during the process、Domestic water source protection and management、Water Conservation、Environmental protection measures guarantee)、Finished product care、Green vegetation restoration project after completion of the project、Environmental Protection Project、Soil and water conservation project (meeting relevant requirements for approval and acceptance),Domestic water and electricity、Coordination of land acquisition and various coordination during construction、Acceptance (including files、Environmental protection、Water Conservation、Firefighting、Safety、Measurement、Occupational Health、Quality supervision and other completion acceptance),And finally deliver the whole process contracting of grid-connected power generation in accordance with the requirements of the contractor。The bidder’s quotation for this project comprehensively considers winter treatment costs and measures。

11.The fan hoisting is single blade hoisting,Wind turbine hoisting、Main crane transition、Assembly and disassembly、And the expansion and repair of transition roads、Issues such as land compensation,Bidders shall consider at their own discretion,The cost is included in the bid price。The main crane is required to use a tire-type 2600T or above crane,No less than 4 main cranes。The auxiliary traction of blade transfer vehicles and tower transfer vehicles is the responsibility of the road construction unit,Bidders shall consider at their own discretion,The cost is included in the bid price。

12.The contractor is solely responsible for local coordination during the construction process (not limited to work interruption caused by any reason、Local government coordination, etc.),The cost is included in the bid price。

13.Fan、Box transformer and hoisting platform within 50mx60m range、Within 6 meters wide of maintenance road、Compensation for land acquisition within 1 mu of each base tower of the collector line and within the booster station,Land acquisition coordination and other temporary land use、Compensation expenses、The contractor is responsible for all formalities and other work。

14.Contractors should fully consider construction disturbance、Crane transition、Line Corridor、Expansion of maintenance road、Road Repair、Compensation for temporary occupation such as opening the fence and opening the door,The required fees should be included in the bid quotation。

15.The contractor is responsible for environmental protection、Land reclamation and vegetation restoration work for soil and water conservation acceptance,The required fees should be fully included in the bid quotation。

16.The contractor is responsible for the grid connection acceptance stage of the project and the standardization after completion、Refinement (identification、flag、Signage) and other related work,The cost is included in the bid price。

17.Quality of general contracting projects by contractors、Safety、Construction period、Be fully responsible for cost and environmental protection。The construction site of this bidding is a smart construction site,Configuring real-time monitoring system at construction site,Monitoring equipment is purchased by the contractor,And use BIM technology to establish a three-dimensional model of the entire wind power project,The bidder fully considers this cost when bidding (see the attachment for specific configuration standards: Project Smart Site Construction Plan)

The contractor of the winning bid section 2 completed the electrical installation of the wind turbine and completed the cable laying in the tower and connected it to the frequency conversion cabinet at the bottom of the tower. The converter was submitted to the bid section 1 after being accepted by the contractor and the supervision unit as meeting the requirements and completed from 32 Box-type transformer installation (including power cable laying and installation from the fan foundation to the low-voltage side of the box-type transformer,All remaining work from the high voltage side of the box transformer to the laying and installation of power cables for 35kV overhead lines。Bidders of Bid Section 1 need to consider the related costs of this part when bidding and quoting,No further consideration after winning the bid。(Bid Section 2 is responsible for the foundation construction of box transformer)

三、Procedures to be processed (the bidder shall set it according to the project conditions,The following is for reference),Including but not limited to the following:

①All temporarily occupied forest land during the entire project、Land、Grassland、Demolition、Cemetery、Compensation、Coordination、The bidder is responsible for all costs and procedures involved in surface attachments (except farmland occupation tax and land use tax);The long-term land lease procedures and related coordination costs shall be handled and borne by the bidder,Long-term land lease fees shall be borne by the tenderer。

② Various procedures from the early stage of the project to the project put into operation (such as: construction permit,Connected to the grid、Water permit, etc.),Environmental protection、Relocation line、Water Conservation、Meteorology (Lightning Protection)、Energy saving、Occupational Health、Earthquake safety evaluation、Firefighting、Safety、Quality Supervision、Special acceptance and procedures for grid connection and other special procedures (obtain relevant documents),And due to government systems、All fees required by the power grid system policy。The bidder coordinates the application for construction land approval letter、Land planning permit、Project Planning Permit、Real estate certificate, etc. (provide file information to the tenderer、Data and other related files)。

The bidder follows environmental protection、Requirements for Soil and Water Conservation Approval Plan,Complete environmental protection、Water conservation construction、Monitoring、Review and Acceptance,Responsible for the repair of all environmental impacts such as soil erosion or vegetation damage caused during the construction process,And complete land reclamation and vegetation restoration work and meet environmental protection requirements、Soil and water conservation acceptance requirements,Implement the three simultaneous tasks of environmental protection, water conservation and water conservation,The required fees should be fully included in the bid quotation。In principle, fixed unit price bidding is based on bill of quantities,Settlement based on the actual amount of work incurred;Requires an assessment of the current status of the site before starting work,If the contractor fails to perform construction in accordance with the requirements, causing damage to water, soil and vegetation beyond the project itself,The resulting costs shall be borne by the contractor and the contracting party has the right to impose penalties,The contractor needs to bear the penalties, fines and other expenses incurred by the local government against the owner。

③Technical services related to this project,If designed together、Micro-site selection review、Factory training、On-site training、Device debugging、Unit trial operation, other electrical equipment warranty period, two-year warranty service, etc.。Application from power grid company、Plan review、Complete all procedures including acceptance;Signing and coordinating power purchase and sale contracts and grid-connected dispatch agreements with State Grid and related companies;Secondary security and grade protection evaluation、Filing procedures;Complete the project lightning protection grounding test in accordance with the requirements of the local meteorological department,Obtain approval document。Equipment installation、Debug、Test、Inspection and testing required by power grid companies at all levels、Host reinforcement、Electric secondary security protection evaluation (switching station、Boost station)、Test、Grid-connected trial operation、Eliminate defects、Acceptance,Process various types of insurance related to the project。Complete acceptance and project handover、Related work on the acceptance of archive materials,And all work related to general contracting projects。

④Responsible for handling lifting equipment safety filing and other related procedures with the local special equipment supervision and management department,And bear corresponding responsibilities;According to relevant standards、Collection of specifications and contract provisions、Organizing all archives during the construction process,Responsible for organizing and transferring owner’s files to the management department;Responsible for coordinating local relations,Protect、Improve construction environment,Pay various mortgage deposits and insurance,We shall bear corresponding responsibilities and fines for related disputes caused by construction reasons;Responsible for coordinating local civil relations during the construction process,The cost is included in the bid price。

⑤The contractor is responsible for connecting to the power grid,Collect project progress and technical information of power grid transmission and transformation supporting projects,Supervise and track its construction progress。

⑥Complete the project acceptance in accordance with the relevant requirements of Gansu Power Grid Company、Start coordination work and various procedures,Complete the registration of the project power quality supervision station and timely organize and coordinate the supervision and acceptance work at each stage;Cooperate with the debugging required to access the contracting party’s centralized control center、Trial operation and other related work; 

⑦ All civil work on site、Local coordination,Civil、All expenses incurred in handling local relations。

⑧Be responsible for handling the above procedures (including costs related to temporary land use、Report preparation fee、Assessment fee、Conference fees, etc.)、Acceptance、All expenses incurred in the process of handling civil relations (land lease expenses、The land reclamation deposit shall be borne by the contractor),If the construction period is delayed due to the bidder's failure to complete relevant procedures in time、Criminal、All administrative penalties and fines shall be borne by the bidder。

⑨Cooperate in providing relevant information and review and acceptance work. 

For details, please refer to the drawings and bill of quantities。For quality reasons,The tenderer has the right to purchase equipment and materials within the scope of the tender、Exercise supervision and veto rights over the process and results of service and professional engineering procurement。 

In case of land rent issue,Resulting in an increase or decrease in the installed capacity,Final settlement will be based on actual installed capacity;If the construction period is extended,In the end, only the construction period was postponed,Bidders are requested to fully consider and prepare construction organization and response measures,Increased costs caused by work delays and shutdowns are included in the bid quotation。

Anyway,The contractor is responsible for power generation from the date of winning the bid until the project is connected to the grid、Handling of policy procedures for the entire completion acceptance process (including but not limited to: power grid、Government、Industry、Various procedures required by the group)。Among them,After the bid deadline,Equipments added due to new policies and new requirements on the power grid、Changes in services and project quantities,Both parties will issue separate visas after approval by the contractor。The contractor seabet app downloadmust fully consider other policy seabet appprocedures and expenses incurred,Relevant costs are all included in the bid quotation。

Because this project is divided into two bids,for fast、Perform the above procedures efficiently,When the entire project needs to be uniformly oriented to the government or regulatory agency (safety supervision、When completing procedures for quality supervision, etc.,The contractor of bid section 1 will take the lead in handling the process,Every contractor of Bid Section 2 cooperates with the specific work;When the entire project needs to go through the grid connection procedures for the power grid,The contractor of bid section 1 will take the lead in handling the process,Every contractor of Bid Section 2 cooperates with the specific work。The processing fee shall be borne by the contractor who takes the lead in the processing。When the procedures for each bidding section do not involve other bidding sections or can be handled independently,Do it yourself and bear the cost。For details, please refer to the quotation list and bidding document attachments for division instructions。

Any form of punishment due to procedural issues in engineering construction projects,The contractors of each bid section shall bear the responsibility。

4. Tools:

The contractor is responsible for purchasing the production operation and maintenance tools necessary for equipment operation and maintenance、Spare parts,Subject to the final approval of the contractor。The production preparation tools listed in the list of production preparation tools (see attachment for details) are all purchased from bid section 1,And bear the corresponding expenses。

5. Other work scope:

Including but not limited to: Project data file organization、Special acceptance of transfer and files,All necessary works are eliminated、Material、Spare parts、Special tools for production safety、Consumables and related technical information and personnel training,Various meetings during the construction period,Project data includes but is not limited to process data、Completion Information。

The contractor is responsible for power generation from the date of winning the bid until the project is connected to the grid、Handling of policy procedures for the entire completion acceptance process (including but not limited to: power grid、Government、Various procedures required by the industry)。Among them,After the bid deadline,Equipments added due to new policies and new requirements on the power grid、Changes in services and project quantities,Both parties will issue separate visas after approval by the contractor。The contractor seabet app downloadmust fully consider other policy seabet appprocedures and expenses incurred,Relevant costs are all included in the bid quotation。

This bidding does not include project supervision, survey and design.

Contractor’s quality of general contracting projects、Safety、Construction period、Be fully responsible for cost and environmental protection。

All income from the electricity sales of this project belongs to Party A.

Procedures encountered during project construction、Coordination、Payment、Work、Acceptance, etc.,Unless the contract clearly stipulates that Party A is responsible,Regardless of whether it is included in the bidding bill of quantities,All belong to the scope of work of Party B。If the bidder cannot respond to all the requirements of the bidding documents,Differences should be clearly stated in a separate document,Otherwise, regardless of whether the content of the bidding document is consistent with the requirements of the bidding document,The bidder shall be deemed to have responded to all requirements of the bidding documents。

Main changes in the defect liability period of this project、GIS、Main power transformation and distribution equipment such as reactive power compensation、Protective equipment、Comprehensive self-system、Communication equipment and accessories for two years,Others are 1 year。

2.1.4Planned construction period (construction)/service period (service)/delivery period (goods):

Planned start time: (The specific start time shall be subject to the written notice of the tenderer),No matter when construction starts,Commissioning time: May 30, 2025。

Milestone node:

1) Start of construction. The specific start time shall be subject to the written notice of the tenderer;

2) Road and platform construction completed January 5, 2025;

3) All construction of the main body of civil construction and equipment foundation of the booster station will be completed on January 22, 2025;

4) All pouring of fan foundation completed on January 22, 2025;

5) All pouring of the transmission line and collector line foundations will be completed on March 10, 2025;

6) Wind turbine hoisting and electrical installation must be completed before May 15, 2025;

7) The booster station will receive power on May 30, 2025; 

8) Full capacity grid connection on May 30, 2025;

9) The remaining relevant procedures for the project shall be completed within the time limit required by the quotation list。(The start time shall be subject to the written notice of the tenderer) The contractor has the right to assess the completion of the wind power milestone plan during the construction period。

The specific construction period shall be subject to the start date issued by the contractor,The first batch of grid connection time will be no later than the commissioning time of (Pingchuan) Beitan 330kV substation project (April 20, 2025),The full-capacity grid connection time is tentatively scheduled for May 30, 2025,The bidder can adjust the progress according to the time requirements of the State Grid for grid connection。

2.1.5Quality requirements: The quality of the project should meet the current national standards and regulations、Specification requirements,Realizing engineering and equipment safety、Stable、Economy、Environmental protection、Long cycle operation,Qualified quality。

3. Bidder qualification requirements 

3.1 Qualifications and performance requirements:

[1]Qualification conditions:

(1) Bid 1 of this project must have the following qualifications:

a.The bidder must be an independent legal person or other organization registered in accordance with the law,Valid supporting documents must be provided。

b.The bidder must have and provide a valid first-level and above qualification certificate for general contracting of power engineering construction。

c.The bidder must have and provide effective decoration (repair)、Trial) Electric Power Facilities License Certificate,Including the installation、The examination requires Level 3 and above。

d.The bidder must have and provide a valid production safety license certificate。

(2) Bid 2 of this project must have the following qualifications:

a.The bidder must be an independent legal person or other organization registered in accordance with the law,Valid supporting documents must be provided。

b.The bidder must have and provide a valid first-level and above qualification certificate for general contracting of power engineering construction。

c.The bidder must have and provide a valid production safety license certificate。

[2]Financial requirements:/

[3] Performance requirements: January 2021 to the bidding deadline (subject to the time of contract signing)

(1) The bidder for Section 1 must have at least EPC or PC general contracting experience for wind farms of 100MW and above (including at least 110kV and above booster stations、35kV and above collector lines、2 contracts for 110kV and above transmission lines and other construction contents,And all have been completed。The bidder must provide a contract that can prove the performance requirements of this bidding and a scanned copy of the corresponding user certificate,The scanned copy of the contract must contain at least: the seal page of the contract between the buyer and the seller、Key information page in contract signing time and performance requirements;User certificate must be stamped by the end user,Can be an acceptance certificate、Proof of use、Return visit records or other materials that can prove that the subject matter of the contract has been completed (if Party A is not the end user,The end-user certificate obtained by Contract Party A is also acceptable)。

(2) Bidders in Section 2 must have at least EPC or PC general contracting experience for wind farms of 100MW and above (including at least wind turbine foundations、2 contracts for wind turbine hoisting and other construction contents,And all have been completed。The bidder must provide a contract that can prove the performance requirements of this bidding and a scanned copy of the corresponding user certificate,The scanned copy of the contract must contain at least: the seal page of the contract between the buyer and the seller、Key information page in contract signing time and performance requirements;User certificate must be stamped by the end user,Can be an acceptance certificate、Proof of use、Return visit records or other materials that can prove that the subject matter of the contract has been completed (if Party A is not the end user,The end-user certificate obtained by Contract Party A is also acceptable)。

[4] Credibility requirements: The bidder’s social credibility self-examination commitment from January 1, 2021 to the present (stamped with the company’s official seal、Customized format);When registering, bidders need to provide the "China Execution Information Disclosure Network" website (http://zxgk on that day.court.gov.cn/shixin/) Screenshot of the webpage to check whether this unit is a person subject to execution for dishonesty。The tenderer shall restrict the dishonest persons subject to execution who are restricted from participating in the bidding activities of engineering construction projects in accordance with the law and regulations。

[5]Project manager qualification requirements:

(1) The bidder must provide the proposed project manager’s valid first-class and above construction engineer qualification registration certificate (construction engineering major or mechanical and electrical engineering major) and a valid safety production assessment certificate (Category B)。

(2) The project manager must have at least 1 experience as a PC or EPC general contracting project manager for wind farms of 100MW and above,The bidder must provide a contract that can prove the performance of the project manager,If there is no project manager name in the contract,The corresponding acceptance certificate or user certificate and other stamped certification materials must be provided (must include project name、Project manager and unit name)。At the same time, the social security certificate of the project manager who has worked for the bidding unit for the past one year must be provided。

[6] Other key personnel requirements:

Technical person in charge: (1) The bidder must provide the proposed construction person in charge with a valid first-class registered construction engineer qualification certificate (construction engineering or mechanical and electrical engineering major) and a valid Class B safety production assessment certificate。(2) Must have at least one experience as the technical person in charge of PC or EPC general contracting for wind farms of 100MW and above,The bidder must provide a contract that can prove the performance of the technical person in charge,If there is no name of the technical person in charge in the contract,The corresponding acceptance certificate or user certificate and other stamped certification materials must be provided (must include project name、Project manager and unit name)。At the same time, it is necessary to provide the social security certificate of the technical person in charge who has worked for the bidding unit for the past one year。

Safety person in charge: The bidder must provide a valid safety production assessment certificate (Category C) of the proposed safety person in charge。

Quality person in charge:/

[7]Other requirements:/

3.2 This project does not accept consortium bids.

4. Obtaining bidding documents

4.1 Bidding participation method: Bidding units need to register on the Sunshine Procurement Service Platform,Search for this project after registration and click to bid to participate,For the operation of the bidding unit, please refer to the "Service Center-Operation Guide" on the homepage (register and click on bidding to participate,No need to apply for CA lock)。

Acquisition time: 09:00 on September 12, 2024 to 17:00 on September 18, 2024,(Beijing time,Except legal holidays),Information required to obtain documents: ①Business license、Qualification Certificate ② Power of Attorney for Legal Representative、The authorized person’s ID card and proof of social security paid by the authorized person in the unit for the past three months ③ Performance contract and corresponding proof of project completion ④ Personnel qualification certificate and relevant proof materials required by personnel ⑤ Remittance of bidding document fees Voucher ⑥ Bidder Information Registration Form,Customized format,Including bidder name、Contact、Contact information、Basic information such as email address。

The bidder shall send a scanned copy of the original documents above (the picture must be clear and legible) (pdf format) to sdzb910@163.com,After successful sending, call the agency for review and confirmation。

4.2 Bidding document price: 750 yuan/copy,No refund upon sale (only business-to-business transfers accepted,Personal transfers are not accepted,Please seabet clubnote the item number when remitting)。

Tender document fee account:

seabet clubCompany name: Shandong Tendering Co., Ltd.

Account opening bank: Bank of China Jinan Wenhua Road Branch

Bank account number: 227305483177

Line number: 104451038330

4.3Potential bidders who have not obtained the bidding documents in accordance with the requirements of this announcement shall not participate in the bidding。

5. Submission of bid documents and bid opening

Submission deadline: 13:30 on October 9, 2024 (Beijing time);

Submission method: Conference Room on the Second Floor, Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

6. Bid opening time and place

Bid opening time: 13:30 on October 9, 2024 (Beijing time);

Bid opening location: Conference Room on the second floor of Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

7. Media for publishing announcements

This bidding announcement is also on the China Bidding and Bidding Public Service Platform (http://www.cebpubservice.com/)、Shandong Procurement and Tendering Network (http://www.sdbidding.org.cn)、Sunshine Procurement Service Platform (http://www.ygcgfw.com/)、Shandong Development Investment Holding Group Co., Ltd. website (https://www.sdfztz.com/)。

8.Contact information

Tenderer: Baiyin Development Investment New Energy Co., Ltd.

Place    Address: Office on the third floor of the single apartment behind Shuiyunchuan Hotel, Pingchuan District, Baiyin City, Gansu Province

Mail    Editor: 730400

Contact person: Xia Weidong

Electricity    Word: 15688338693

Email: /

Tendering agency: Shandong Tendering Co., Ltd.

Place    Address: No. 13, Wenhua West Road, Lixia District, Jinan City

Mail    Editor: 250000

Contact person: Liu Gong

Electricity    Tel: 0531-81917677、15069174047

E-mail: sdzb910@163.com





Shandong Development Investment Holding Group Co., Ltd.      Copyright 2019 All rights reserved      Lu ICP No. 16018610

Address: Shandong Development Building, the intersection of Haiyou Road and Xingong North Street, Lixia District, Jinan City, Shandong Province     

Share