1.Tender conditions

The name of this bidding project is: Baiyin Jingtai Development New Energy Co., Ltd. (Jingtai) Area C 200,000 kilowatt wind power project construction general contracting (PC) project,Project bidding number is: 0627-24101941959,The tenderer is: Baiyin Jingtai Development New Energy Co., Ltd.,The project unit is: Baiyin Jingtai Development New Energy Co., Ltd.,The source of funds is self-raised by the enterprise。The bidding agency is Shandong Tendering Co., Ltd.。This project has met the bidding conditions,Now inviting bids for this project。

2. Project Overview and Bidding Scope

2.1 Project Overview, Bidding Scope and Bid Section (Package) Division

2.1.1 Project Overview

Wufo Township, County,The average altitude is about 1700 meters-1820 meters, Proposed land 2. 9437 hectares。The straight-line distance between the wind farm and Jingtai County is about 20km,About 80km from Baiyin City。There is highway G2012 on the north side of the wind farm area,There are highway G1816, Uma Expressway and national highway G338 passing by on the west side,Convenient external transportation。The installed capacity of this wind power project is 200MW,A total of 32 units installed with a single machine capacity of 6.25MW wind turbine set,Planned to connect to the 110 kV booster station of the 200,000 kilowatt wind power project in Zone C (Jingtai) through 8 35 kV collector lines,Sent out by the newly built 110 kV booster station and lines of the wind power project in Area C, Connect to the planned 330 kV substation。

This project is divided into one bidding section:

Mainly including but not limited to the following: equipment procurement required for this project,Boost station civil construction and electrical installation project、Wind farm road and platform construction、Wind power equipment foundation pouring and equipment installation、Collection line construction、Water conservation and greening construction and other projects,Various insurances,Land、Forestry、Grid connection and other procedures,Water Conservation、Environmental protection、Safety、Occupational Health、Fire protection, etc. acceptance record,With the government、Power Grid、Land、Forestry、Related coordination with villagers, etc.,Trial run、Transfer、All related work including warranty period services, cooperation process settlement and completion settlement。

2.1.2 Bidding Scope:

Baiyin Jingtai Development New Energy Co., Ltd. (Jingtai) Area C 200,000 kilowatt wind power project construction general contracting (PC) project,Mainly including but not limited to:

1.Meet all the installed capacity of this project、Secondary equipment,Including but not limited to: all equipment except A-supplied equipment,Including but not limited to power distribution devices in booster stations、Switch cabinet、Boost station secondary cable、All equipment and materials of the collector line (including tower materials、Gold tools、Wire、Insulator、Attachment、Optical cable, etc.),Electrical secondary equipment (including comprehensive automation、Network-related equipment、Communication Equipment、Remote control system、Security monitoring equipment, etc.)、Material (Server、Switch、Firewall、router、Longitudinal encryption device (including fans, etc.) and corresponding spare parts、Special tools、All software and hardware equipment such as instruments and meters and corresponding technical services and fire protection、Security facilities。If the tenderer provides a recommended purchase list, the bidder shall purchase from the tenderer's recommended list,Included into total bid price。Equipment procurement should be strictly carried out in accordance with the technical specifications and recommendation list provided by the tenderer。The equipment purchased by the bidder must ensure that it meets the requirements of local power grid access。

2.Supply equipment: wind turbines、Tower,The equipment supplied by A is not included in the total contract price;

3.Including production scheduling of the above equipment、Urgent delivery、Transport、Pick up、Unlucky (including storage yard)、Acceptance of goods、Warehousing, storage, etc. (The equipment purchased by the contractor is also entrusted to the contractor for production scheduling、Expediting goods、Receive goods、Keeping、Full process control of bad luck (including yard construction) etc.,The contractor is responsible for equipment relocation and storage site coordination and expenses caused by any reason。

4.The bidder arranges to supply A (wind turbine unit、Supervision and inspection of equipment outside the tower。Out of consideration for procurement quality,The tenderer has the right to purchase equipment within the scope of the tender、Exercise supervision and decision-making rights over the process and results of service and professional engineering procurement。The tenderer has the right to supply all equipment within the bidding scope based on the progress of the project。

5.All A-supplied equipment and all equipment within seabet betting platformthe bidding scope of this project、Transportation of secondary equipment、Loading and unloading、Installation and Debugging、Keeping、The bidder shall be responsible for any second misfortune。

6.Construction unit before equipment procurement、The supervision unit will review the construction drawings and technical specifications,Only after the review is correct, the general contractor can proceed with bidding, procurement and construction。The bidder must be comprehensive、Comprehensively consider the quotation。

7.Bidders should consider the period and before and after major national, provincial and municipal events,Major equipment production and transportation,The bidder shall make the lead time for large equipment transportation according to the overall construction period requirements of the bidder。

8.Above equipment、Material、Technical services such as spare parts、Performance testing and provision of related technical information, etc.。The contractor is obliged to assist、Cooperate with the contractor to connect with the design institute、Picture reminder work。Because the project’s single access system plan has not yet been approved,All drawings and equipment technical specifications in this bidding document are only used for PC general contracting bidding,The equipment within the bidding scope must meet the technical specifications of the later design institute、Related technical requirements of power grid companies。Construction unit before equipment procurement、The supervision unit will review the construction drawings and technical specifications,Only after the review is correct, the general contractor can proceed with bidding, procurement and construction。The bidder must be comprehensive、Comprehensively consider the quotation。

2. Construction scope:

Civil construction that meets the grid-connected operation and acceptance of the project、Wind turbine installation、Electrical installation、Debug、Grid connection、Trial run,Acceptance and defect elimination at each stage of the project,Water Conservation、Environmental protection、Safety、Occupational health and other “three simultaneous” and other related work,Special acceptance of each project,Personnel training and final delivery operations,Quality warranty service within the warranty period,Cooperate with settlement、Completion final accounts audit and all related work。Specifically include but are not limited to the following:

1.Civil works: including booster station、Grading and earthwork works in wind farm、Road works (including on-site roads,Including new roads and old road repairs)、Wind turbine foundation project、Box transformer foundation project、Water Conservation and Greening Project、Environmental Protection Project、Water supply and drainage project、Cable trench engineering、Line Basics、Ancillary facilities engineering、All civil construction related work including various equipment foundation projects。

2.Electrical installation work: all primary and secondary equipment installation、Debug,includes、Box transformer installation project、Cable Engineering、Grounding system engineering、Video surveillance system engineering、Collection line project、Wind power prediction system、Monitoring background monitoring system、Reserved interfaces and channels for centralized control center、All equipment debugging and unit testing、Overall system debugging、Handover test and acceptance test of the complete system performance test equipment after grid connection、All engineering equipment、Facilities、Environmental signage、Production of safety signs、Installation and other related work。

3. The bidder follows Gansu Province’s design standards for wind power project vegetation restoration operations、Vegetation restoration plan report of this project、Land Reclamation Plan、Environmental protection、Requirements for Soil and Water Conservation Approval Plan,Implement environmental protection、Three simultaneous water and water conservation、Comprehensive land utilization work,The required costs should be fully included in the bid quotation。Under construction,Responsible for ecological environment protection within the construction scope、Domestic water source protection,Take necessary water conservation、Environmental protection measures,Rucao Square、Spread grass seeds and cover with green netting,After the completion of construction, we are responsible for completing the repair work of all environmental impacts such as soil erosion or vegetation damage within the construction scope,Complete vegetation restoration and planting within and around the construction area,The vegetation restoration and greening planting and maintenance period is two years,Finally ensure that the survival rate is not lower than the water conservation approval requirements,And ensure that the project finally passes environmental protection、Soil and water conservation acceptance requirements,All required costs are included in the bid quotation,Results in forestry due to the reasons of the bidder、Land、Water Conservation、Environmental protection、Criminal administrative penalties from cultural relics and other related departments,The consequences and related handling and coordination shall be borne by the bidder,The bidder shall bear the relevant costs;The bidder needs to evaluate the current situation of the site before starting work,If the bidder fails to perform construction in accordance with the requirements, causing damage to water, soil and vegetation beyond the project itself,The resulting costs shall be borne by the bidder,And the tenderer has the right to punish the bidder,The bidder needs to bear the penalties, fines and other fees and administrative criminal penalties incurred by the local government on the bidder。

4.Various construction measures during the construction period,Such as construction precipitation、Drainage、Winter rainy season、High temperature construction, etc.,included in the quotation of each construction list item。

5.Applying for various insurances,Including but not limited to construction personnel employer’s liability insurance、Accident insurance、Equipment and material transportation insurance、Construction Equipment Insurance、Safety production liability insurance、And other insurance required by local regulatory authorities、Policy insurance required by national laws and regulations, etc.,Included in bid price,Do not list separately。

6.According to the latest system of project quality acceptance management of the tenderer,Complete key node acceptance、Phase acceptance and defect elimination work。

7.According to relevant standards、Collection of specifications and contract provisions、Organize all archives during the project construction process,Responsible for organizing and transferring the files to the tenderer’s file management department (the information must be organized in accordance with the latest regulations on the tenderer’s information management,Transfer the archives that meet the requirements of the tenderer,And complete the arrangement on schedule、Transfer and archive)。

8.Others not Seabetspecified but belong to the construction of this project、Trial run、Acceptance、Transfer、Warranty service during the warranty period、Related work such as settlement auditing。All projects before handover、The equipment will be kept and cared for by the winning bidder,Any damage、If lost, the winning bidder will be responsible for repair or replacement,And bear the corresponding expenses。

9.The bidder must strictly implement the various rules and regulations issued by the tenderer and the tenderer’s superior unit during the construction process,Such as "New Energy Power Generation Enterprise Safety Visualization Standard Management Manual"、"Measures for the Management of Safety Video Monitoring of New Energy Construction Projects"、"Wind Farm Safety and Civilized Construction Manual"、"Standardized Atlas of Safe and Civilized Construction of New Energy Engineering Construction"、"New Energy Engineering Construction Safety Standardization Management Manual"、"Wind Power Station Project Engineering Acceptance Management Regulations" and other related documents (if there are new regulations issued above,Follow the new regulations),Meet the relevant requirements of the above documents,And the relevant costs are included in the total bid price。

10.The transmission line project includes the 110kV booster station gantry (line side) to the 330kV substation 110kV gantry (line side),Including the last wire insulators on both sides、Gold tools、Wire,Not including lower drainage line、T-type wire clamp procurement and construction。The 330KV substation side communication optical cable is led from the ground pole to the 110kV booster station optical cable connection box (the connection box is included in this contract),And the procurement and laying of optical fiber materials from the connection box to the 330-station communication cabinet、Light board、Ethernet board system board procurement、Access,Installation and debugging work。Bidders need to consider this related cost when bidding and quoting,No further consideration will be given after winning the bid。

11.The fan hoisting is single blade hoisting,Wind turbine hoisting、Main crane transition、Assembly and disassembly、And the expansion and repair of transition roads、Issues such as land compensation,Bidders shall consider at their own discretion,The cost is included in the bid price。The main crane is required to use a tire-type 2600T or above crane,No less than 4 main cranes。The auxiliary traction of blade transfer vehicles and tower transfer vehicles is the responsibility of the road construction unit,Bidders shall consider at their own discretion,The cost is included in the bid price。

12.Corridor for line construction、Roads and Transportation、Issues such as land compensation,Bidders shall consider at their own discretion,The cost is included in the bid price。

13.The contractor is solely responsible for local coordination during the construction process (not limited to interruptions caused by any reason、Local government coordination, etc.),The cost is included in the bid price。

14.Fan、Within the range of 50mx60m of box transformer and hoisting platform、Within 6 meters of the maintenance road、Compensation for land acquisition within 1 mu of each base tower of the collector line and the booster station,Land acquisition coordination and other temporary land use、Compensation expenses、The contractor is responsible for all formalities and other work。

15.Contractors should fully consider construction disturbance、Crane transition、Line Corridor、Expansion of maintenance road、Road Repair、Compensation for temporary occupation such as opening the fence and opening the door,The required fees should be included in the bid quotation。

16.The contractor is responsible for environmental protection、Construction monitoring review and acceptance of water conservation,Land reclamation and vegetation restoration work,The required costs should be fully included in the bid quotation。

17.The contractor is responsible for the grid connection acceptance stage of the project and the standardization after completion、Refinement (identification、flag、Signage) and other related work,The cost is included in the bid price。

三、Scope of procedures (including fees),Including but not limited to the following:

①All temporarily occupied forest land during the entire project、Land、Grassland、Demolition、Cemetery、Compensation、Coordination、The bidder is responsible for all costs and procedures involved in surface attachments (except farmland occupation tax and land use tax);The long-term land lease procedures and related coordination costs shall be handled and borne by the bidder,Long-term land lease fees shall be borne by the tenderer。

② Various procedures from the early stage of the project to the project put into operation (such as: construction permit,Grid connection、Water permit, etc.),Environmental protection、Relocation line、Water Conservation、Meteorology (Lightning Protection)、Energy saving、Occupational Health、Earthquake safety evaluation、Firefighting、Safety、Quality Supervision、Special acceptance and procedures for grid connection and other matters (obtain relevant documents),And due to government systems、All fees required by power grid system policies。The bidder coordinates the application for construction land approval letter、Land planning permit、Project Planning Permit、Real estate certificate, etc. (provide file information to the tenderer、Data and other related files)。

The bidder follows environmental protection、Requirements for Soil and Water Conservation Approval Plan,Responsible for the repair of all environmental impacts such as soil erosion or vegetation damage caused during the construction process,And complete land reclamation and vegetation restoration work and meet environmental protection requirements、Soil and water conservation acceptance requirements,Implement the three simultaneous tasks of environmental protection, water conservation,The required costs should be fully included in the bid quotation。In principle, fixed unit price bidding is based on bill of quantities,Settlement will be based on the actual engineering volume;Requires an assessment of the current status of the site before starting work,If the contractor fails to perform construction in accordance with the requirements, causing damage to water, soil and vegetation beyond the project itself,The resulting costs shall be borne by the contractor and the contracting party has the right to impose penalties,The contractor needs to bear the penalties, fines and other expenses incurred by the local government against the owner。

③Technical services related to this project,If designed together、Micro-site selection review、Factory training、On-site training、Device debugging、Unit trial operation, other electrical equipment warranty period, two-year warranty service, etc.。Application from power grid company、Plan review、Complete all procedures including acceptance;Signing and coordinating power purchase and sale contracts and grid-connected dispatch agreements with State Grid and related companies;Secondary security and grade protection evaluation、Filing procedures;Complete seabet betting platformthe project lightning protection grounding test in accordance with the requirements of the local meteorological department,Obtain approval document。Equipment installation、Debug、Test、Inspection and testing required by power grid companies at all levels、Host hardening、Electric secondary security protection evaluation (switching station、Boost station)、Test、Grid-connected trial operation、Eliminate defects、Acceptance,Process various types of insurance related to the project。Complete acceptance and project handover、Related work on the acceptance of archives,And all work related to general contracting projects。

④Responsible for handling lifting equipment safety filing and other related procedures with the local special equipment supervision and management department,And bear corresponding responsibilities;According to relevant standards、Collection of specifications and contract provisions、Organize all archives during the project construction process,Responsible for organizing and handing over the owner’s files to the management department;Responsible for coordinating local relations,Protect、Improve construction environment,Pay various mortgages and insurance,We shall bear corresponding responsibilities and fines for related disputes caused by construction reasons;Responsible for coordinating local civil relations during the construction process,The cost is included in the bid price。

⑤The contractor is responsible for connecting to the power grid,Collect project progress and technical information of power grid transmission and transformation supporting projects,Supervise and track its construction progress。

⑥Complete the project acceptance in accordance with the relevant requirements of Gansu Power Grid Company、Start coordination work and various procedures,Complete the registration of the project power quality supervision station and timely organize and coordinate the supervision and acceptance work at each stage;Cooperate with the debugging required to access the contracting party’s centralized control center、Trial operation and other related work; 

⑦ All civil work on site、Local coordination,Civil、All expenses incurred in handling local relations。

⑧Be responsible for handling the above procedures (including costs related to temporary land use、Report preparation fee、Assessment fee、Conference fees, etc.)、Acceptance、All expenses incurred in the process of handling civil relations (land lease expenses、The land reclamation deposit shall be borne by the contractor),If the construction period is delayed due to the bidder's failure to complete relevant procedures in time、Criminal、All administrative penalties and fines shall be borne by the bidder。

⑨Cooperate in providing relevant information and review、Acceptance work。 For details, please refer to the drawings and bill of quantities。For quality reasons,The tenderer has the right to purchase equipment and materials within the scope of the tender、Exercise supervision and veto rights over the process and results of service and professional engineering procurement。 In case of land rent issue,Resulting in an increase or decrease in the installed capacity,Final settlement will be based on actual installed capacity;If it causes an extension of the construction period,In the end, only the construction period was postponed,Bidders are requested to fully consider and prepare construction organization and response measures,Increased costs caused by work delays and shutdowns are included in the bid quotation。

Anyway,The contractor is responsible from the date of winning the bid until the project is connected to the grid for power generation、Handling of policy procedures for the entire completion acceptance process (including but not limited to: power grid、Government、Industry、Various procedures required by the group)。Among them,After the bid deadline,Equipments added due to new policies and new requirements of the power grid、Changes in services and project quantities,Both parties will issue separate visas after approval by the contractor。The contractor must fully consider other policy procedures and expenses incurred,Relevant costs are all included in the bid quotation。

(4) Quality of the contractor’s general contracting project、Safety、Construction period、Be fully responsible for cost and environmental protection。The construction site of this bidding is a smart construction site,Configuring real-time monitoring system at construction site,Monitoring equipment is purchased by the contractor,Bidders should fully consider this cost when bidding (see attachment)。

four、Tools: Party B is responsible for purchasing the production operation and maintenance tools necessary for equipment operation and maintenance、Spare parts,Subject to Party A’s final approval,And bear the corresponding expenses (see attachment)。

2.1.3 Project duration

Planned start time: The specific start time shall be subject to the written notice of the tenderer,Whenever construction starts,The production date is May 30, 2025。

Milestone node:

1) The road construction within the wind farm has started: the specific start time shall be subject to the written notice of the tenderer;

2) Road and platform construction completed before January 5, 2025;

3) All pouring of the fan foundation will be completed before January 22, 2025;

4) All pouring of the collector line foundation will be completed before March 10, 2025;

5) All construction of the main civil construction and equipment foundation of the booster station will be completed before January 22, 2025;

6) Wind turbine hoisting and electrical installation must be completed before May 15, 2025;

7) The booster station will receive power before May 30, 2025; 

8) Full capacity grid connection before May 30, 2025;

9) The remaining relevant procedures for the project shall be completed within the time limit required by the quotation list。(The start time shall be subject to the written notice of the tenderer) The contractor has the right to assess the completion of the wind power milestone plan during the construction period。

2.1.4 Others: The quality of the project should meet current national standards and regulations、Specification requirements,Qualified quality,Realizing engineering and equipment safety、Stable、Economy、Environmental protection、Long cycle operation。

3. Bidder qualification requirements

3.1 Qualifications and performance requirements:

[1]Qualification conditions:

(1) The bidder must be an independent legal person or other organization registered in accordance with the law,Valid supporting documents must be provided。

(2) The bidder must have and provide a valid first-level and above qualification certificate for general contracting of power engineering construction。

(3) The bidder must have and provide valid installation (repair)、Trial) Electric Power Facilities License Certificate,Including the installation、The examination requires Level 3 and above。

(4) The bidder must have and provide a valid production safety license certificate。

[2]Financial requirements:/

[3] Performance requirements: September 2021 to the bidding deadline (subject to the time of contract signing),The bidder must have at least EPC or PC general contracting experience for wind farms of 100MW and above (including at least 110kV and above booster stations、Fan basics、seabet mobile35kV and above collector lines、2 contracts for wind turbine hoisting construction content,And all have been completed。The bidder must provide a contract that can prove the performance requirements of this bidding and a scanned copy of the corresponding user certificate,The scanned copy of the contract must contain at least: the seal page of the contract between the buyer and the seller、Key information page in contract signing time and performance requirements;User certificate must be stamped by the end user,It can be an acceptance certificate、Proof of use、Return visit records or other materials that can prove that the subject matter of the contract has been completed (if Party A is not the end user,The end-user certificate obtained by Contract Party A is also acceptable)。

[4] Reputation requirements: /

[5]Project manager qualification requirements:

(1) The bidder must provide the proposed project manager’s valid first-class and above construction engineer qualification registration certificate (construction engineering major or mechanical and electrical engineering major) and a valid safety production assessment certificate (Category B)。

(2) The project manager must have at least one experience as a PC or EPC general contracting project manager for wind farms of 100MW and above,The bidder must provide a contract that can prove the performance of the project manager,If there is no project manager name in the contract,The corresponding acceptance certificate or user certificate and other stamped certification materials must be provided (must include project name、Project manager and unit name)。At the same time, the social security certificate of the project manager who has worked for the bidding unit for the past one year must be provided。

[6] Other key personnel requirements:

Technical person in charge: The bidder must provide the proposed construction person in charge with a valid first-level registered construction engineer qualification certificate (construction engineering or mechanical and electrical engineering major) and a valid Class B safety production assessment certificate。

The technical person in charge must have at least one experience as the technical person in charge of PC or EPC general contracting for wind farms of 100MW and above,The bidder must provide a contract that can prove the performance of the technical person in charge,If there is no name of the technical person in charge in the contract,The corresponding acceptance certificate or user certificate and other stamped certification materials must be provided (must include project name、Technical person in charge and unit name)。At the same time, it is necessary to provide the social security certificate of the technical person in charge who has worked for the bidding unit for the past one year。

Safety person in charge: The bidder must provide a valid safety production assessment certificate (Category C) of the proposed safety person in charge。

 Quality person in charge:/

[7]Other requirements: According to the bidding document format requirements,Provide "Letter of Commitment",Failed to provide or modify the promised content,The bid will be rejected。

3.2 This project does not accept consortium bids. 

4. Obtaining bidding documents

4.1 Bidding participation method: Bidding units need to register on the Sunshine Procurement Service Platform,Search for the project after registration and click to bid to participate,For the operation of the bidding unit, please refer to the "Service Center-Operation Guide" on the homepage (register and click on bidding to participate,No need to apply for CA lock)。Acquisition time: 09:00 on September 12, 2024 to 17:00 on September 18, 2024,(Beijing time,Except statutory holidays),Information required to obtain documents: ①Business license、Qualification certificate②Power of attorney for legal representative、The authorized person’s ID card and proof of social security paid by the authorized person in the unit for the past three months ③Performance contract and corresponding certification materials for project completion ④Personnel qualification certificate and relevant certification materials required by personnel ⑤Remittance of bidding document fees Voucher ⑥ Bidder Information Registration Form,Customized format,Including bidder’s name、Contact、Contact information、Basic information such as email address。The bidder shall send a scanned copy of the original documents above (the picture must be clear and legible) (pdf format) to sdzb910@163.com,After successful sending, call the agency for review and confirmation。

4.2 Bidding document price: 750 yuan/copy,No refund upon sale (only business-to-business transfers accepted,Personal transfers are not accepted,Please note the item number when remitting)。Tender document expense account: Company name: Shandong Tendering Co., Ltd.;Account opening bank: Bank of China Jinan Wenhua Road Branch;Bank account number: 227305483177;Line number: 104451038330。

4.3Potential bidders who have not obtained the bidding documents in accordance with the requirements of this announcement shall not participate in the bidding。

5. Submission of bid documents and bid opening

Submission deadline: 09:00 on October 9, 2024 (Beijing time);

Submission method: Conference Room on the Second Floor, Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

6. Bid opening time and place

Bid opening time: 09:00 on October 9, 2024 (Beijing time);

Bid opening location: Conference Room on the second floor of Block A, Haichen Building, No. 13 Wenhua West Road, Lixia District, Jinan City。

7. Media for publishing announcements

This bidding announcement is also on the China Bidding and Bidding Public Service Platform (http://www.cebpubservice.com/)、Shandong Procurement and Tendering Network (http://www.sdbidding.org.cn)、Sunshine Procurement Service Platform (http://www.ygcgfw.com/)、Shandong Development Investment Holding Group Co., Ltd. website (https://www.sdfztz.com/)。

8.Contact information

Tenderer: Baiyin Jingtai Development New Energy Co., Ltd.

Place    Address: No. 58, Shawo Village, Shangshawo Town, Jingtai County, Baiyin City, Gansu Province

Mail    Editor: 730400

Contact person: Xia Weidong

Electricity    Voice: 15688338693

Email: 1452337444@qq.com

Tendering agency: Shandong Tendering Co., Ltd.

Place    Address: No. 13, Wenhua West Road, Lixia District, Jinan City

Mail    Editor: 250000

Contact person: Manager Liu

Electricity    Call: 0531-81917677、15069174047

Email: sdzb910@163.com





Shandong Development Investment Holding Group Co., Ltd.      Copyright 2019 All rights reserved      Lu ICP No. 16018610

Address: Shandong Development Building, the intersection of Haiyou Road and Xingong North Street, Lixia District, Jinan City, Shandong Province     

Share